Line 5 Eglinton

Line 5 Eglinton
Overview
OwnerMetrolinx
LocaleToronto, Ontario, Canada
Mississauga, Ontario, Canada (phase 2)
Termini
Stations25 (7 under construction)
WebsiteOfficial route page
Service
TypeLight rail
SystemToronto subway
Operator(s)Toronto Transit Commission[1]
Depot(s)Eglinton Maintenance and Storage Facility
Rolling stockFlexity Freedom
History
Planned openingWest extension: 2031; 5 years' time (2031)[2]
OpenedFebruary 8, 2026; 21 days ago (2026-02-08)[3]
Technical
Line length
  • 19 km (12 mi)
  • 9.2 km (5.7 mi) (under construction)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
ElectrificationOverhead line750 V DC[4]
Operating speed
  • In tunnel: 80 km/h (50 mph)
  • On surface: 60 km/h (37 mph)[5]
SignallingAlstom Cityflo 650 CBTC[6]
Route map
Map
Map of the Eglinton Crosstown and all connections. Map by OpenStreetMap.
To Pearson Airport (proposed)
Renforth
Mississauga Transitway
Martin Grove
Kipling
Islington
Royal York
Scarlett
Jane
Phase 2
Phase 1
Mount Dennis
Keelesdale
Caledonia
Fairbank
Oakwood
Cedarvale
Forest Hill
Chaplin
Avenue
Eglinton
Mount Pleasant
Leaside
Laird
Sunnybrook Park
Don Valley
Ontario Line (future)
Aga Khan Park & Museum
Wynford
Sloane
O'Connor
Pharmacy
Hakimi Lebovic
Golden Mile
Birchmount
Ionview
Kennedy (GO)
Line 2 to McCowan/Sheppard (future)
Handicapped/disabled access All stations are accessible

Line 5 Eglinton, also known as the Eglinton Crosstown LRT or the Crosstown, is a light rail transit line that is part of the Toronto subway system in Toronto, Ontario, Canada. It has 25 stations and is 19 kilometres (11.8 mi) long. Service on the line began on February 8, 2026, as part of a phased opening.

Owned by Metrolinx and operated by the Toronto Transit Commission (TTC), the line was conceived in 2007 during the administration of Toronto mayor David Miller as part of Transit City, a large-scale transit expansion plan that included several light rail lines proposed across the city. While the plan was later dropped by successive municipal governments, only the Eglinton Crosstown LRT received support and funding from the Government of Ontario under Premier Kathleen Wynne.[7]

The line was constructed in two phases. The first phase of the 19-kilometre (12 mi) line includes 25 stops along Eglinton Avenue, from Mount Dennis station mostly underground to Laird station, after which it runs predominantly at-grade within the street's median to Kennedy station in Scarborough, where it connects underground with Line 2 Bloor–Danforth. Automatic train control is used in the tunnelled sections. This first phase had an estimated cost of CA$12.82 billion;[8] the cost when the contract was awarded was pegged at $9.1 billion, although the cost was originally estimated at $11 billion.[9]

A second phase, a 9.2-kilometre (5.7 mi) westward extension from Mount Dennis, will run mostly underground or elevated to Renforth station, with seven new stations. The second phase is expected to cost $4.7 billion and to be completed by 2031. Construction of the westward extension to Renforth station began in July 2021. The extension would bring the Toronto subway system into Mississauga.[2][10][11]

Two future extensions were planned: an eastern extension to the University of Toronto Scarborough[12] and a northwestern extension towards Toronto Pearson International Airport.[13] In 2022, the city of Toronto converted the eastern extension into a city project and a separate line known as the Eglinton East LRT using light rail technology incompatible with the Line 5 technology.

Construction of the first phase of the line began in 2011 and was originally planned to be complete in 2020,[14] but the opening date was revised several times, with Metrolinx next expecting the line to be substantially complete by September 2022.[15] After revising the opening date of the central section to 2023 and then, amid ongoing legal action against Crosslinx (the construction consortium), Metrolinx stated they believed there was no credible schedule to complete the project.[16][17][18][19] By September 2023, the central section was estimated to be 97 percent complete, although Metrolinx refused to provide an estimated completion date.[20][21] On December 2, 2025, after a 30-day trial of the line, Metrolinx announced it would hand over operations to the TTC, which would determine an opening date.[22] In early February 2026, the TTC set February 8, 2026, as the start date for a phased opening.[3]

History

[edit]

Background

[edit]

The origins of Line 5 Eglinton can be traced to the 1985 Network 2011 plan conceived by the Metropolitan Toronto government. The plan included a busway along Eglinton Avenue, to be completed by 2003. In 1986, a coalition of City of York and Etobicoke Metro councillors and the Regional Municipality of Peel persuaded Metro Council to include an Eglinton West line in a new Transit Network Plan.[23][24] Work on a new 4-kilometre (2.5 mi) subway line began in 1994 at an estimated cost of $740 million, with the line extending the subway westwards from Cedarvale station (then known as Eglinton West station) to Black Creek Drive.[25] However, construction was halted following the election in 1995,[26] which saw Mike Harris take power and led to the cancellation of the Eglinton West line, with the existing tunnel quickly filled in.[27]

Original concept

[edit]
Billboard promoting the Transit City project in 2008

Line 5 Eglinton was originally conceived as the Eglinton Crosstown LRT, a partially underground light rail line, announced in 2007 by Toronto mayor David Miller and TTC chair Adam Giambrone. It was part of the Transit City plan, which included the implementation of six other light rail lines across Toronto. The original version of the line would have run from Pearson Airport along Silver Dart Drive to Convair Drive. The line would have then turned southwest to a bridge over Highway 401 to reach Commerce Boulevard on the other side, where it would run south to reach Eglinton Avenue and the east end of the Mississauga Transitway. The rest of the line would run east along Eglinton Avenue, including a portion along which the cancelled Eglinton West subway line would have been built. The line would then traverse the city, connecting with Line 1 Yonge–University, Line 2 Bloor–Danforth, and Line 3 Scarborough.

There were 43 stops planned for the Eglinton Crosstown LRT, 13 of which would be underground.[28] Surface stops would be spaced on average 500 metres (550 yd) apart and the underground stations would be 850 m (930 yd) apart on average, as constructing numerous underground stops would be costly. The average speed would be 28 kilometres per hour (17 mph),[29][30] compared with the existing bus routes along Eglinton that have an average speed of 16 to 18 km/h (9.9 to 11.2 mph).[31] The line would terminate at Kennedy station to the east in Scarborough where it would meet Line 2 Bloor–Danforth, the proposed Scarborough Malvern LRT and GO Transit's Stouffville line. The expected cost was CA$4.6 billion.[32] As a result of provincial funding cuts, construction of the line was divided into two phases: phase one would end at Jane Street, and phase two would terminate as had been planned at the Toronto Pearson International Airport.[33]

Rob Ford–era redesigns

[edit]

Miller's successor, Rob Ford, announced the cancellation of Transit City on December 1, 2010, the day he took office.[34] He proposed an alternative titled the "Eglinton–Scarborough Crosstown line", which put the 19-kilometre (12 mi) line along Eglinton Avenue completely underground. The line would have then followed the route of Line 3 Scarborough, thus forming a single line continuously from Black Creek Drive to McCowan. The cost would almost double to $8.2 billion and, compared to the original plan, 18 fewer stops were planned, including the elimination of the connection to Pearson Airport. Most of the additional cost would have come from putting 12 additional stations underground and for converting the Scarborough RT.

On February 8, 2012, in a special meeting, Toronto City Council, led by Karen Stintz, voted 25–18 to override Mayor Ford's modifications to the project.[35] The vote reinstated the original proposal to only construct the portion between Laird Drive and Keele Street underground while the remainder of the line is built along the surface.[35] On November 30, 2012, the environmental assessment was revised, such that the east tunnel portal location would be moved from east of Brentcliffe to east of Don Mills;[36] however, this was reversed in May 2013 after receiving community feedback.[37] In January 2013, city councillors from Scarborough put forward an alternative plan to proceed with the construction of the Eglinton Avenue portion of the line as planned but to exclude the Scarborough RT. In July 2013, plans for an "Eglinton-Scarborough Crosstown" line were abandoned, thereby reverting the entire line back to the plan that had been conceived under Transit City.[38][39]

Location of tracks at Leslie Street

[edit]

In 2012, Metrolinx discovered that there would be minimal cost differential between tunnelling under the West Don River at Leslie Street (the proposed location of the Sunnybrook Park stop) versus laying the track on the surface. Metrolinx also stated that tunnelling through that section would have provided "significant improvements to construction staging, schedule and traffic impacts".[40][41] Thus, in December 2012, Metrolinx proposed an extension of the tunnel and eliminating the planned Sunnybrook Park surface stop. An underground station at Sunnybrook was considered too expensive given low projected ridership. Local residents objected to the elimination of their stop,[42] and by mid-2013, Metrolinx had relented and the surface stop had been restored.[40][43]

Construction and implementation

[edit]
Promotional logo of the construction project, incorporating the Toronto Subway typeface

Procurement

[edit]

The line was built in two separate phases. To expedite construction, tunnelling took place first, followed by construction of stations, rail and other systems.

Tunnelling

[edit]

In July 2010, Metrolinx ordered four tunnel boring machines (TBMs) from Lovat for $54 million.[44][45] Each TBM was 10 metres (33 ft) long, 6.5 metres (21 ft) in diameter, and weighed 400 tonnes (390 long tons; 440 short tons).[46] The TBMs were named Dennis, Lea, Don, and Humber, after Mount Dennis, Leaside, the Don River, and the Humber River, respectively.[47][48] The names Dennis and Lea were chosen in reference to Canadian poet Dennis Lee.[48]

In September 2012, Metrolinx awarded a $320-million contract to Crosstown Transit Constructors (a joint venture between Obayashi, Kenny Construction, Kenaidan Contracting and Technicore Underground) to dig a 6.2-kilometre (3.9 mi) tunnel from Black Creek Drive to Yonge Street.[49] In November 2013, Metrolinx awarded a $177-million contract to Aecon and ACS Infrastructure Canada / Dragados to dig a 3.25-kilometre (2.02 mi) tunnel from Brentcliffe Road to Yonge Street.[50]

Stations and other infrastructure

[edit]

In January 2013, Infrastructure Ontario issued a request for qualifications (RFQ) to shortlist companies that would design, build, finance and maintain the line as part of a public–private partnership.[51] The contract would include the design, construction and commissioning of:

  • 25 new stops and stations
  • track, power, signalling and other mechanical and electrical systems
  • a vehicle maintenance and storage facility
  • a new train storage facility

The contract would also include financing of the project, as well as maintenance of the line for a period of 30 years.[51]

In December 2013, Infrastructure Ontario and Metrolinx released a request for proposals (RFP). Two teams were shortlisted through the RFQ process – Crosslinx Transit Solutions (a consortium including SNC-Lavalin, ACS Infrastructure Canada, EllisDon, Aecon, Dragados and IBI Group) and Crosstown Transit Partners (a consortium including Strabag, Bechtel, Obayashi, Fengate Capital Management and OHL Concesiones).[52][53] The RFP process closed in February 2015.[54]

In June 2015, Infrastructure Ontario and Metrolinx announced that Crosslinx Transit Solutions had been selected.[55] In November 2015, Ontario Minister of Transportation Steven Del Duca announced that Crosslinx Transit Solutions had been awarded the contract at a cost of $9.1 billion.[56][57] Del Duca noted this was around $2 billion less than estimated.[58]

At the time of contract award, the 30-year contract to build and maintain the line totalled $9.1 billion, with an opening date of 2021. Capital costs would be $5.3 billion, with each of the 15 underground stations costing $80–$100 million to build and the ten street-level stops $3–$5 million each. The remainder will be for financing, lifecycle and maintenance costs.[59][58] Upon completion of the line, its costs had risen to $12.8 billion owing to construction delays and consequences of the COVID-19 pandemic.[60]

Construction timeline

[edit]

Tunnelling (2010–2015)

[edit]
Cutting face of TBM Don being extracted just east of Eglinton station in 2017

In August 2011, preparation for construction of a launch shaft for tunnel boring machines at Black Creek Drive began,[61] while in October of that year, the first part of tunnel construction started.[62] On November 9, 2011, in Keelesdale Park, Mayor Rob Ford and Premier Dalton McGuinty officially broke ground on the new project.[63] In May 2012, the TTC considered that a 2020 opening date was unlikely and that a more realistic in-service date would be between 2022 and 2023. The main reason given was that the project management had been transferred from the TTC to Infrastructure Ontario. A private contractor would complete the project, effectively requiring that contractor to redo all design work already completed by the TTC.[64]

In February 2013, TBMs Dennis and Lea arrived in Keelesdale Park.[65] In June 2013, the TBMs Dennis and Lea began tunnelling on the line. Traffic on Eglinton Avenue near Keele Street was reduced to one lane in each direction.[66]

In March 2014, work began at Brentcliffe Road to set up the eastern launch shaft.[67] By April 2014, the TBMs had arrived at Caledonia station.[68] In April 2014, The Globe and Mail reported that the two western tunnel boring machines were excavating "approximately 1,000 cubic yards [760 m3] of spoil" per day.[69] For the year prior to May 2014, the two TBMs Dennis and Lea had been excavating and installing concrete tunnel liners at a rate of approximately 10 metres (33 ft) per day.[70] The tunnels were lined with precast concrete liner segments. Six 2.5-tonne (2.8-ton) segments form each ring. In early December 2014, Dennis and Lea arrived at Eglinton West station.[71] Dennis stopped to allow Lea to catch up so that they would arrive at Eglinton West station at the same time.

On the weekend of April 18 and 19, 2015, the tunnel boring machines Dennis and Lea were lifted out of a shaft west of Allen Road and moved about 100 metres (330 ft) to a shaft just east of Allen Road.[72] In April 2015, merchants along Eglinton Avenue West were complaining of lost revenue (up to a 35 percent dip in sales), because construction was discouraging customers with snarled traffic, limited parking options, reduced foot traffic and dusty sidewalks.[73] On September 24, 2015, Transportation Minister Steven Del Duca issued a statement saying the Crosstown would not operate until September 2021, in order "to mitigate disruption to the local community and infrastructure as much as possible". The earlier plan had been to open in 2020 with tunnelling and station construction to start in 2012.[74] In September 2015, TBM Don started to bore the north tunnel from the Brentcliffe Road launching site westwards towards Yonge Street. TBM Humber would start boring the south tunnel approximately one month later.[75]

In February 2016, work began on the extraction shaft for TBMs Humber and Don, which bored the eastern segment of the line.[76][67]

In May 2016, TBMs Dennis and Lea, both of which had been boring the western segment of the line, completed their work by reaching Yonge Street.[77] Dennis and Lea had bored 6.4 kilometres (4.0 mi), installing 25,647 precast concrete tunnel segments to construct the 4,279 rings to line the twin tunnels.[78] In August 2016, TBMs Don and Humber, which had been boring the eastern segment of the line, completed their work by reaching Yonge Street. Don and Humber bored 3.3 kilometres (2.1 mi), installing 26,178 precast concrete tunnel segments to construct the 4,363 rings to line the twin tunnels.[78][79] The TBMs were then removed in pieces from the extraction shaft on Eglinton Avenue just east of Yonge Street.[80][81]

In March 2020, Crosslinx began work to extract tunnel boring machines Dennis and Lea at Duplex Avenue, one block west of Yonge Street.[82]

Stations, systems and commissioning (2016–2026)

[edit]
2016–2020
[edit]
Future site of Forest Hill station; the façade of the former House of Chan restaurant unintentionally collapsed, injuring several passersby. Laying rails at the O'Connor stop in April 2019

On March 10, 2016, Ontario premier Kathleen Wynne and Toronto mayor John Tory attended a ground-breaking ceremony at the site of Keelesdale station, the first station on which construction was to start. The project was slated for completion in 2021.[83]

On April 18, 2016, at the site of the future Forest Hill station, the façade of the former House of Chan restaurant and the scaffolding that was holding it up collapsed, injuring seven people.[84]

In July 2017, construction crews began preparations for constructing the eastern at-grade portion of the line by removing the median in the roadway.[85][86] A month later, the first section of track was installed at the Eglinton Maintenance and Storage Facility (EMSF).[85] In October 2018, the EMSF was substantially complete.[87] By December 2018, 10 kilometres (6.2 mi) of the 47 kilometres (29 mi) of track had been installed.[87] In January 2019, Bombardier delivered the first Flexity Freedom light rail vehicle (LRV) to the facility,[88] and the first concrete was poured for the surface section at the location of the future O'Connor stop at Victoria Park Avenue.[89]

In November 2019, Crosslinx informed Metrolinx that it did not expect the line to be completed before May 6, 2022, and that the construction costs would total $12.58 billion, an increase of $330 million over previous estimates. The main problems reported were defective caissons (underground watertight compartments) built in the 1950s at Eglinton station, groundwater at the Avenue station site and construction difficulties at the Canadian Pacific Kansas City (CPKC) / Metrolinx bridge adjacent to the Mount Dennis station.[90]

In December 2019, track clearance testing using LRVs began between the EMSF and the Western portal. On December 17, Crosslinx conducted an inaugural run with staff and guests from the handover platform at the EMSF to the elevated guideway over Black Creek Drive. At that time, overhead wire had been installed between the EMSF to just short of the Keelesdale platform.[91][92] By January 2020, Crosslinx had laid 50 percent of the line's track.[93]

The next month, Metrolinx announced that the line would not open until "well into 2022", a delay from the previous target of September 2021.[94] This was despite Metrolinx reaching a settlement with Crosslinx the previous year and paying the consortium $237 million to commit to a September 2021 deadline.[90] Metrolinx cited reasons for the delay: Crosslinx had started work nine months late, and had been slow to finalize some aspects of the design.[95]

In March 2020, the provincial government announced it would provide $3 million in aid to local merchants negatively affected by Crosstown construction near their businesses. The Ministry of Transportation and Metrolinx also announced that they would look into an earlier, partial opening of the line.[96]

The same month, Crosslinx installed the first passenger-waiting shelter on the surface section of the line at the Pharmacy stop.[97] On May 4, 2020, Metrolinx reported the first test trip by a light rail vehicle (LRV) in a Line 5 tunnel. The trip was from the maintenance and storage facility to just short of the underground Keelesdale station. The test run was to check clearances, trackwork, and overhead power and communications; it involved several movements in and out of the tunnel at speeds of up to 25 km/h (16 mph).[98]

In October 2020, Crosslinx proposed partially opening Line 5 in February 2022, although Eglinton station would not be fully completed until September 2022. Crosslinx said defective infrastructure from 1954 at Eglinton station, difficult hydrogeological conditions and the COVID-19 pandemic had hindered the project. Moody's Investors Service also reported delays at Kennedy, Forest Hill, Mount Pleasant and Cedarvale stations.[99] On October 8, Crosslinx filed a lawsuit against Metrolinx and Infrastructure Ontario, claiming $134 million in unexpected costs due to the pandemic. Metrolinx countered that Crosslinx had been falling behind schedule before the pandemic.[100]

In December 2020, the first pieces of artwork were being installed at Science Centre (later Don Valley) and Mount Dennis stations.[101]

2021
[edit]
Line 5 LRVs manufactured by Bombardier, used for testing, parked at Brentcliffe portal in September 2021

By April 2021, 85 percent of track had been installed along the entire line.[102] Later that month, the last base-level concrete pour on the line was completed at Eglinton station.[103] That May, Crosslinx energized the overhead catenary system between Laird and Kennedy stations for testing.[104][105]

On May 17, Crosslinx won a case in Ontario Superior Court against Metrolinx and Infrastructure Ontario to allow compensation for the extra construction costs and project delays due to the pandemic. The court decision allowed Crosslinx to negotiate with the two provincial agencies for financial compensation and a later completion date. (The completion per the contract was to have been September 2021, later revised to 2022 by Metrolinx.) Crosslinx sought approximately $134 million in compensation for extra safety measures, absenteeism and supply-chain problems due to the COVID-19 pandemic.[106]

In the third quarter of 2021, six LRVs were transferred to the eastern end of the line for testing on the surface section east of the Brentcliffe portal.[107][108] In November, trackage along the line was 100 percent complete, with the last section of track laid at Eglinton station.[109][110] The same month, the first LRVs were tested along the western underground section to and from the EMSF.[111]

By December, Metrolinx and Infrastructure Ontario had come to a settlement with Crosslinx to pay the consortium an extra $325 million to handle additional costs due the COVID-19 pandemic and due to an unexpected obstruction at Eglinton station that was impeding construction. The line was expected to be substantially complete by September 2022 but possibly not be open until 2023.[112]

2022
[edit]
New southwest entrance to Eglinton station under construction in July 2022

By late February 2022, the last signal to control LRT train movements along the line was installed in the tunnel at Laird station.[113]

In March 2022, Metrolinx announced that all 76 of the light rail vehicles had been brought together at the Eglinton Maintenance and Storage Facility, the fleet's final deliveries having arrived in 2021.[114]

In July 2022, Metrolinx started to test three-car trains together with the train control system along the line. Three cars is the maximum train length for the line and can carry up to 490 passengers.[115]

In late September 2022, Metrolinx announced that Crosslinx was behind schedule and thus Line 5 would not be completed by year-end as had been previously expected. Metrolinx did not provide a revised completion date.[116] However, CBC Toronto cited an unnamed source with knowledge of the project who stated that Line 5 would likely be delayed a year, until September 2023. The completion of underground stations was behind schedule, particularly at Eglinton station where tunnelling under Line 1 was difficult.[117]

According to an internal Metrolinx report from September 2022, Crosslinx had expected to complete the project by March 2023, but Metrolinx felt that date to be unrealistic. Metrolinx blamed Crosslinx and old infrastructure at Eglinton station for project delays. Metrolinx also had complaints about deficiencies in work completed. Crosslinx had over $260 million in outstanding claims against Metrolinx.[118]

In December, CBC Toronto obtained confidential documents from Metrolinx which indicated that the company did not believe Crosslinx had a "credible plan" to complete the line. The records stated that 98 percent of construction and engineering work was completed at the time of their writing, while only 79 percent of track and train testing had been completed.[118]

2023
[edit]
By 2023, the bulk of major construction had been completed

In February 2023, Crosslinx reported it had made good progress at Eglinton station, but some utility and road restoration work still needed to be done. By April 2023, Metrolinx had not given a project status update to the public since September 2022. Documents obtained by the Toronto Star indicated the silence from Metrolinx was at the direction of the provincial government.[119]

In late April 2023, construction crews started to remove the platform at the Sloane stop due to uneven concrete, which was causing water to pool on the platform. Replacement of the platform (built in 2020) would take one month of work, and Metrolinx said that Crosslinx would be responsible for the cost.[120]

On April 26, 2023, Brian Lilley of the Toronto Sun cited unnamed sources in government and industry who indicated that Line 5 would not open until 2024 at the earliest.[121] A day later, Metrolinx CEO Phil Verster gave a status report but gave no completion date. The project had 260 non-conformance issues for Crosslinx to fix. The major problem identified was improperly laid tracks in tunnels that might be only a few millimetres out of gauge but could result in a derailment. Testing was only 50 percent complete. Training of TTC staff to operate the line would not start until the line was fully ready.[122]

On May 14, 2023, the TTC opened the northern platform extension at Eglinton station along Line 1 Yonge–University so that Line 1 trains stop 24 metres (79 ft) further north. Upon Line 5's opening, the northern extension would offer riders a more convenient transfer between trains on Lines 1 and 5. The southern end of the original platform is closed off from trains but is still publicly accessible from the centre of the island platform to allow for access to the elevator.[123]

In May 2023, Metrolinx announced that Crosslinx intended to sue the provincial agency and also to cease working with the TTC on the project. Crosslinx claimed that changes requested by the TTC were creating project delays and extra costs and that this resulted from a lack of a signed operating agreement between Metrolinx and the TTC. Crosslinx wanted the courts to remove its obligation to work on the project while issues with Metrolinx and the TTC remained unresolved. On the same day, Verster confirmed the line would not open until sometime in 2024.[124]

In the fourth quarter of 2023, Verster announced he would not give an estimated opening date for Line 5 until after "high-risk testing and commissioning work [was] completed" and that the date would be announced three months before opening.[125][126] As of September 2023, there were about 200 unresolved defects on the project.[126] Crosslinx president Bill Gifford said a key piece of work could not be done in the winter months.[125]

By December 2023, 15.3 percent of the integration testing had been completed. Ten test trains were operating along the line, but testing would require increased train frequencies of three to five minutes. Training of TTC operators was 12 percent complete.[125] In December 2023, for budget purposes, the TTC made the assumption that Line 5 would open no earlier than September 2024.[127]

2024
[edit]

In March 2024, Metrolinx CEO Phil Verster stated that all major construction had been completed but that the most serious obstacle remaining was defects in software for the signalling and train control system.[128] The software defects were corrected with the sixth version of the software tested in April and May 2024.[129]

A Metrolinx report dated June 27, 2024, indicated that construction had been completed for 14 of the 15 stations along the line. Eglinton station was the only station where work was outstanding due to its complexity. By June 2024, 17 TTC staff had been trained as instructors. It was planned they would, in turn, train 110 operators.[129]

By early October 2024, Metrolinx stated that Line 5 would not open in 2024, but that it would give three months notice of its opening.[130] On December 4, 2024, Councillor Jamaal Myers, chairman of the TTC board, stated that the TTC did not expect Line 5 to open before June 1, 2025, at the earliest. Myers also said he had no confirmation from Metrolinx as to whether that date was realistic. As of December 2024, training of TTC operators had not been completed, and a 30-day test period of non-revenue service had not started.[131]

2025
[edit]
TTC bus stop in June 2025 on Eglinton Avenue showing service changes for when Line 5 opens

In March 2025, two anonymous sources told the Toronto Star that the line was expected to open in September 2025. One remarked upon the possibility of "an eleventh-hour problem" due to Metrolinx's lack of transparency regarding the construction and testing of the project.[132] In June 2025, Premier Ford stated he had confidence in a September 2025 start of operations.[133]

On March 28, 2025, Metrolinx announced that, due to the permanent closure of the Ontario Science Centre's original Don Mills site a year prior, Science Centre station would be renamed Don Valley to reflect the station's proximity to the Don Valley Parkway, the Don River, and the Don Valley itself. Other names considered for the station were Concorde, Industrial District, Olympia Square, Ferrand, and Don River.[134]

In mid-June 2025, Metrolinx handed over the operation of Line 5 to the Toronto Transit Commission. The TTC's command centre took over the line from Line 5's backup control centre. By this time, all TTC vehicle operators had been trained. Stress testing of the system remained in progress.[135] In July 2025, the TTC noted that the September opening was unlikely but that opening in the fourth quarter of 2025 was "plausible" and that the line would be open by the end of the year.[136]

At the beginning of August 2025, Michael Lindsay, the CEO of Metrolinx, announced that during stress testing, the Flexity Freedom vehicles had issues with "availability and reliability" due to the vehicles lying unused for ten years. Metrolinx needed to establish a "maintenance profile" for the vehicles.[137] After addressing these issues, Metrolinx started a "revenue demonstration" on October 7, where trains would run on a full schedule without passengers for at least 30 days. Metrolinx indicated it would require three weeks of problem-free running before opening the line for passenger service.[138]

On December 2, 2025, a 30-day trial of the line was successfully completed. As a result, Metrolinx began the approximately two-week process of turning over the line to the TTC, which would then in turn set an opening date.[22] On December 5, 2025, the Ontario government announced that the project had been substantially completed.[139]

On December 16, 2025, city council approved a motion by Mayor Olivia Chow to have the city manager coordinate with the TTC and Metrolinx about implementing better signal priority on the surface portion of Line 5. This was to avoid the implementation problems that resulted in excessively long run times on Line 6 Finch West.[140]

2026
[edit]

In January 2026, the random activation of emergency brakes on trains gave the TTC cause for concern as a critical safety issue. Multiple braking errors occurred on January 7, but only four more occurred during the remainder of the month. With emergency braking, there is no jolting stop but rather a gradual deceleration. Metrolinx believed the problem was not serious enough to delay opening the line, but the TTC insisted on a satisfactory explanation of the problem from Metrolinx.[141] In early February 2026, the TTC announced a phased opening would begin February 8, 2026.[3] The line subsequently opened on February 8, 2026.[142]

A phased opening of the line is being undertaken to follow the recommendations from a public inquiry into the launch of the O-Train's Line 1 (also known as the Confederation Line) in Ottawa. During this period, the TTC plans to make service adjustments to fine-tune operations, and Line 5 service will end early at 11 p.m. Train speed in the tunnel will be limited to 60 kilometres per hour (37 mph), and the end-to-end run time will be 50 to 55 minutes versus 105 minutes for a bus. Transit priority over left-turning road traffic was expected to be implemented in late February. When full service begins, trains will operate to 1 a.m., and the tunnel speed will be raised to a maximum of 80 kilometres per hour (50 mph).[143][144]

Route description

[edit]
Schematic map of Line 5 Eglinton (orange; with thin line representing street-running sections), including the under-construction Eglinton Crosstown west extension to Renforth (dark orange). Also shown are portions of the future Scarborough subway extension (dark green) north and east of Kennedy, and the Ontario Line (blue).
View of a green track segment from a Line 5 train at Birchmount Road Snowed-over green track on the line's surface section just west of Birchmount Road

Line 5 Eglinton begins at the surface Mount Dennis station and heads east, immediately crossing a wye to the Eglinton Maintenance and Storage Facility to the north. After passing over Black Creek Drive, it enters a tunnel portal to begin its approximately 10 km (6.2 mi) underground run.[145][146] At Cedarvale station, it interchanges with the western branch of Line 1 Yonge–University, and then passes a diamond crossover just east of the platform. Immediately east of Avenue station, it enters a large-diameter tunnel section containing both service tracks and a third centre track used to store trains. It interchanges with the eastern branch of Line 1 at Eglinton station (located at Yonge Street), and traverses another crossover. The easternmost underground station, Laird, hosts both a crossover and a centre track, both housed within single tunnels to the west and east respectively.

The line then rises to the surface at a tunnel portal at Brentliffe Road to begin its run along the median of Eglinton Avenue and uses "green track", which is track with vegetation growing beside and between the rails, with paved gaps at intersections and stops.[147] It soon reaches the first on-street surface stop, Sunnybrook Park, at Leslie Street, next to the overpass for the CPKC Belleville Subdivision. Approaching Don Mills Road, it dives underground and arrives at Don Valley station, an underground through-station within the surface section. East of Don Valley, it rises to the surface for another 6 km (3.7 mi), serving nine more surface stops, with several crossovers in between along this section, and a centre track at Sloane.[148] The line returns underground at its eastern terminus at Kennedy station, which provides connections with Line 2 Bloor–Danforth (which also has Kennedy as its eastern terminus) and GO Transit's Stouffville line.

Design

[edit]

The underground sections consist mostly of twin tunnels bored with TBMs and stations built using the cut-and-cover method. However, Avenue, Laird, and Oakwood stations were constructed using the sequential excavation method (SEM). The mined caverns at Avenue and Laird both contain their train platforms as well as their aforementioned adjacent special trackwork in single semicircular tubes. According to Crosslinx, SEM is more common in Europe and Line 5 was the first project to use the technique in Toronto.[149]

On-street stops are located at signalized intersections and have platforms with level boarding, barriers along the street to protect waiting passengers, Presto machines, screens displaying the next vehicle arrival time and advertising, platform illumination, and covered glass waiting shelters with benches and an assistance intercom for passenger security.[150][151]

Each section of green track has irrigation chambers, a water supply, and a power source for the irrigation system. Green track dampens train sounds, absorbs runoff water, reduces ambient temperatures in summer, and minimizes the spread of dust.[152]

Stations and stops

[edit]
Station/stop[153] Type Notes Connections
Mount Dennis Surface Located east of Weston Road in the Mount Dennis neighbourhood Kitchener line, Union Pearson Express
Keelesdale Underground Located at Keele Street in the Keelesdale (or Silverthorne) neighbourhood
Caledonia Underground Future connection to Barrie line; indirect connection to Beltline Trail
Fairbank Underground Located at Dufferin Street in the Fairbank neighbourhood
Oakwood Underground
Cedarvale Underground Located at Allen Road in the Humewood–Cedarvale neighbourhood, formerly named Eglinton West until 2025 and was opened as a Line 1 station in 1978.[154][155] Yonge–University
Forest Hill Underground Located at Bathurst Street in the Forest Hill neighbourhood
Chaplin Underground Indirect connection to Beltline Trail
Avenue Underground
Eglinton Underground Located at Yonge Street, in the Yonge-Eglinton neighbourhood; opened as original northern terminus station of Line 1 in 1954 Yonge–University
Mount Pleasant Underground
Leaside Underground Located at Bayview Avenue in the Leaside neighbourhood
Laird Underground
Sunnybrook Park On-street Parallel side platforms located at Leslie Street near Sunnybrook Park[156]
Don Valley Underground Located at Don Mills Road; renamed from Science Centre prior to opening[134] Future connection to Ontario Line
Aga Khan Park & Museum On-street Parallel side platforms located on the west side of the Don Valley Parkway, near its namesake Aga Khan Park and Aga Khan Museum[157]
Wynford On-street Parallel side platforms just west of the bridge over Wynford Drive[158]
Sloane On-street Centre platform located east of the Sloane Avenue and Bermondsey Road intersection[159]
O'Connor On-street Parallel side platforms between Victoria Park Avenue and Eglinton Square (extension of the namesake O'Connor Drive)[160]
Pharmacy On-street Parallel side platforms[161]
Hakimi Lebovic On-street Far-side platforms[162]
Golden Mile On-street Far-side platforms located at Warden Avenue in the Golden Mile neighbourhood[163]
Birchmount On-street Parallel side platforms[164]
Ionview On-street Parallel side platforms[165]
Kennedy Underground Bloor–Danforth and Kennedy GO Station for Stouffville line

Station names

[edit]
Fairbank station platform name signage with Dufferin Street as a subtitleSign at Eglinton West station in November 2025 advising of its name change to Cedarvale

During the early planning stages of Line 5 Eglinton, numerous stations and stops received temporary working names that closely resembled or duplicated those of existing Toronto subway and GO Transit stations. To prevent confusion among passengers, a report presented to the TTC board in November 2015 recommended giving unique names to all stations within the system, including those on Line 5. Thus, the stations and even on-street stops with non-unique working names were given permanent names that mostly reflected the surrounding neighbourhoods: for instance, the stations at Weston Road and Dufferin Street were given the names Mount Dennis and Fairbank respectively, and the stop at Warden Avenue was named Golden Mile.[166]

The working names of some on-street stops were not used as final names even though they did not conflict with existing station names. The Aga Khan Park & Museum stop was given the working name Ferrand after the nearby Ferrand Drive,[167][157] and Sloane had the working name Bermondsey.

Initially, the stop at Hakimi Avenue and Lebovic Road had the working name Lebovic. Metrolinx renamed it Hakimi after the TTC noted that Hakimi Avenue offered access to prominent local landmarks, such as Centennial College's Ashtonbee Campus.[154][168] Ultimately, the stop was named Hakimi Lebovic after both streets.

To avoid confusion with Eglinton station, Eglinton West station was renamed Cedarvale in 2025.[154][169]

Following the permanent closure of the Ontario Science Centre in June 2024, it was decided to rename the unopened Science Centre station.[170][171] The name Don Valley was chosen in March 2025.[134]

All the line's grade-separated stations are subtitled with the cross street under the station name on the platform walls, even if they are actually named after said streets (e.g. Fairbank–Dufferin Street and Oakwood–Oakwood Avenue).

As of 2026, alternate names for stations along the under-construction western extension at cross streets (Kipling Avenue, Islington Avenue, Royal York Road, Jane Street, and Martin Grove Road) that conflict with the names of existing stations or stops on Line 2 Bloor–Danforth and Line 6 Finch West have not been announced.

Public art and architecture

[edit]
Station architecture at Keelesdale station

Architecture

[edit]

The architectural concept for the line was designed by architects gh3* from Toronto and Daoust Lestage Lizotte Stecker from Montreal. Specific stations were then designed by Arcadis, Dialog and NORR, with surface stops designed by Arcadis.[172][173] Beth Kapusta, the former head of design excellence at Metrolinx, described the theme of the line as "simple, light-filled boxes", and that it would be a "strong, coherent system of clarity and simplicity".[172]

Architectural features of station buildings include natural light from large windows and skylights, steel structures painted white, and orange accents (the colour of the line).[174][175] The Toronto Subway typeface is used both on supergraphics (station names screen-printed onto glass at street level) as well as on platform wall signage.[172] The entrances to Chaplin, Keelesdale, and Fairbank station are set in landscaped plazas with planting and seating.[174]

The design of each station is similar, with all having island platforms with white structural elements and white concourse levels that follow the theme of Metrolinx's GO stations. The station names are emblazoned on the platform walls along wide strips coloured either black, grey, or orange and placed over unadorned concrete that displays them in a standard size over a pattern of vertical white dots, which is broken by the names in larger-size block letters extending the full height of the strips.[172][176]

Reviewing the line, Alex Bozikovic, the architecture critic of The Globe and Mail, stated that the line was, "in architectural terms, a modest success despite its troubled beginnings",[177] with Azure magazine calling the design "sensitive and streamlined".[174]

Two heritage buildings were reused as part of the line – the main entrance at Mount Pleasant station uses the façade of a former branch of the Imperial Bank of Canada (later CIBC) in a building originally designed by architect Herbert Horner in 1928, and Mount Dennis station uses Kodak Building 9 (a former industrial building) as the station building.[178][179]

Total Lunar Eclipse by artist Sarah Morris at Don Valley station

Public art

[edit]

Eight stations along the line feature artworks.[180] Six of the eight stations (Mount Dennis, Caledonia, Cedarvale, Eglinton, Don Valley and Kennedy) were chosen because they are all interchange stations expected to host higher passenger volumes.[181][182] All artworks are integrated into station design and construction rather than being stand-alone pieces. The art budget was about $10 million. About $1 million of that budget was to be used for digital art to appear on screens at stations along the line.[181]

Because of the controversy surrounding the artwork LightSpell at Line 1's Pioneer Village station, in which commuters could have displayed inappropriate messages that violate TTC By-Law No. 1, none of the Line 5 artworks are interactive.

Operations

[edit]

Operating characteristics of the line include:

  • There will be three types of train control on the line. Automatic train control (ATC) without a driver onboard is used within the Eglinton Maintenance and Storage Facility. In the underground segment between Mount Dennis and Laird stations, a driver will operate train doors and push a button to depart a station, with ATC controlling the train until the next station. Between Laird and Kennedy stations, the driver controls all train functions.[183][184]
  • On the surface, the line will have dedicated right-of-way transit lanes separate from regular traffic[29] and usage of priority signalling at intersections to ensure certainty in travel times – unlike the streetcars in downtown Toronto and southern Etobicoke or on St. Clair Avenue in midtown Toronto.[151]
  • Light rail vehicles and subway trains can both travel up to 80 kilometres per hour (50 mph). However, actual speed is determined by the spacing of the stops and the dwell times at stops. Line 5 vehicles were planned have an average speed of 28 kilometres per hour (17 mph). As a comparison, the average speed of the Line 2 Bloor–Danforth subway is 32 kilometres per hour (20 mph).[185] The maximum operating speed is 80 kilometres per hour (50 mph) on the tunnelled portion of the line and 60 kilometres per hour (37 mph) on the street-level sections.[5]
  • The projected ridership of the line is 5,400 passengers per hour in the peak direction by 2031, but the capacity of the vehicles is 15,000 passengers per hour per direction.[29]
  • The surface section of the line runs on a proof-of-payment system but the underground stations will have subway-type fare gates and staff; Presto cards will be available for use across the entire line.[186]
  • Metrolinx requires 76 Flexity Freedom LRVs to operate the line.[187]
  • Annual operating and maintenance costs are estimated to be $80 million upon opening of the line. However, fare revenue and the costs saved by eliminating Eglinton bus service would result in a net annual cost of $39 million.[188]
  • There are a total of 12 crossovers along the line to reverse LRT trains—seven at underground stations and five on the surface section. Avenue and Laird stations also have a storage track (with Laird having both)[clarification needed] that trains can enter and exit in either direction. The storage tracks can accommodate a train in case of an emergency or change in service as well as allowing for a change of direction.[189]
  • Line 5 uses a guideway intrusion detection system (GIDS) to detect trespassers on the tracks on the underground sections of the line. When GIDS detects a trespasser on the tracks, it will issue an audio warning to the trespasser, provide live CCTV video to central control, and automatically stop the train without driver intervention. Each station will have ten GIDS scanners, five on each side of the platform. There are also GIDS scanners at each tunnel portal. In addition, there are three scanners within the yellow tactile strips at each platform edge to issue an audio warning if a person steps on it before the train has arrived.[190]

Rolling stock

[edit]
Flexity Freedom light rail vehicle, built by Bombardier

As the line is owned by the province of Ontario, Metrolinx chose the Bombardier Flexity Freedom light rail vehicle, which uses standard gauge rather than the TTC's own slightly larger gauge. Metrolinx wanted to avoid using a custom gauge in order to secure a better price from the manufacturer and to create a standard for other light-rail projects in the province.[191] The vehicles have an operator's cab at only one end of the vehicle; thus, the LRVs must be run in back-to-back coupled pairs.[192] Trains use automatic train control within the tunnelled portion of the line.[183] Like the Flexity Outlook vehicles Bombardier built for the TTC's streetcar system, initial work building the chassis was performed at Bombardier's Mexican plant in Ciudad Sahagún, Hidalgo, with final assembly at Bombardier's plant in Thunder Bay.[193]

In 2010, Metrolinx ordered 182 Flexity Freedom vehicles not only for Line 5 but for other light-rail projects in Ontario. The first two deliveries were expected in the second quarter of 2015 but had not arrived by May 2017. After being unsure if a timely delivery of the Bombardier vehicle order could be relied upon, Metrolinx reduced the Bombardier order from 182 to 76 to supply just Line 5 and made a contingency order with Alstom for 61 Citadis Spirit vehicles, of which 44 would be for Line 5 and the remaining 17 for Line 6 Finch West.[194] If the Flexity Freedom order did arrive after all, surplus Alstom vehicles would be used on other Metrolinx projects (most likely the Hurontario LRT in Mississauga in Peel Region).[195][196] On October 30, 2018, Bombardier announced that the first Flexity Freedom vehicle had completed its in-house testing and would be delivered for on-site testing in Toronto in November 2018.[197] However, the first vehicle arrived late, on January 8, 2019.[198] As a commissioning test, each vehicle must travel at least 600 km (370 mi) before accepting passengers.[199]

Aerial view of the Eglinton Maintenance and Storage Facility in 2024

Eglinton Maintenance and Storage Facility

[edit]

A maintenance and storage facility is required for Line 5, given the new technology employed, track gauge and the number of vehicles ordered. The Eglinton Maintenance and Storage Facility (EMSF) has storage for 162 Flexity Freedom LRT vehicles and has extensive maintenance facilities to keep them running smoothly.[200] The facility is located near the line's western terminus at Mount Dennis station on lands formerly occupied by Kodak's Toronto campus[201][202][203] and near the Mount Dennis bus garage.

The site includes a backup power facility adjacent to the CN/CP rail corridor at the northwest corner of the EMSF. In the event of a widespread power outage, the new facility will provide Line 5 vehicles with up to four hours of electrical power. The facility will use lithium-ion batteries, which will be charged overnight in order to reduce peak-period power demands and operating costs. The batteries will have a capacity of 10 MW / 30 MWh, equivalent to what is needed to power 8000 homes for a year. The roof of the facility will have about 250 solar panels to generate 90 kW DC of electricity.[204]

Extension to Renforth and Pearson Airport

[edit]
Construction of Humber River bridge piers in October 2025

The line is being extended west of Mount Dennis station to Renforth, the eastern terminal station of the existing Mississauga Transitway, a bus rapid transit line in the adjacent City of Mississauga. The 9.2-kilometre (6-mile) extension will add seven new stations – four underground, two elevated and one within an open trench. Preliminary construction work began in 2020 when the first phase of Line 5 was still under construction, with the tunnelling contract awarded in 2021. Forecast to serve 96,700 daily riders, the project was estimated in 2026 to cost $3.97 billion to construct.[205][206] Metrolinx has proposed extending the line farther still to Toronto Pearson International Airport in the future.[207]

Eglinton East LRT

[edit]

Under Mayor John Tory, Toronto City Council approved an eastern extension for Line 5 Eglinton on March 31, 2016,[13] and it is a City of Toronto project still in the proposal stage. However, in May 2022, the Eglinton East LRT (EELRT) became a proposal for a separate line rather than an extension of Line 5.[208]: 1, 2 

Between 2016 and 2021, the City of Toronto proposed that the EELRT be an eastward extension of Line 5 Eglinton, extending from Kennedy station to Malvern Town Centre via Eglinton Avenue East, Kingston Road and Morningside Avenue. By 2022, the city had decided that the EELRT would be a separate, independent line with no rail connection to Line 5 at Kennedy station. Unlike Line 5 Eglinton and its western extension, which are Metrolinx projects, the EELRT is a City of Toronto project.[208]

By 2022, city planning staff had concluded a through-service connection with Line 5 at Kennedy station was not feasible as an EELRT tunnel would be only 2 metres (6 ft 7 in) above the SSE tunnel at Kennedy station, and the SSE tunnel structure would not be strong enough to safely support an EELRT tunnel above it.[209]: 24  As a separate line, the EELRT would use trains 50 metres (160 ft) long or less. The EELRT would use its own distinct vehicles (i.e. different from those used on Line 5 Eglinton) in order to better adapt to the line's conditions: no running in tunnels, shorter trains and platforms, and a better ability to climb steeper grades to avoid expensive road infrastructure changes that would otherwise be required if the EELRT were a Line 5 extension.[208]: 8  It would also connect with Line 2 again at Sheppard Avenue East and McCowan Road.

See also

[edit]

References

[edit]
  1. ^ Consiglio, Alex (October 3, 2012). "TTC to operate city's new LRT lines". Toronto Star. Archived from the original on November 3, 2012. Retrieved November 1, 2012.
  2. ^ a b "Eglinton Crosstown West Extension - FAQs". Metrolinx. Retrieved December 7, 2023.
  3. ^ a b c Thayaparan, Arrthy (February 8, 2026). "Beautiful, wonderful, or Toronto transit's black eye? Whatever it is, the Eglinton Crosstown is finally open". CBC News. Archived from the original on February 9, 2026. Retrieved February 9, 2026.
  4. ^ "Eglinton LRT 2012 update" (PDF). Metrolinx. February 2012. Archived from the original (PDF) on February 13, 2013. Retrieved November 1, 2013.
  5. ^ a b "Eglinton Crosstown LRT vehicles hit top speeds". Metrolinx. May 6, 2022. Archived from the original on May 6, 2022.
  6. ^ "Bombardier's Rail Control Division Further Expands North American Presence". Bombardier Transportation. October 8, 2015. Archived from the original on January 9, 2019. Retrieved May 18, 2020.
  7. ^ "Ontario Newsroom".
  8. ^ "No 'credible plan' for completion of Eglinton LRT, says Metrolinx". Toronto Star. December 12, 2022. Archived from the original on December 9, 2022. Retrieved December 9, 2022.
  9. ^ Kalinowski, Tess (November 3, 2015). "$9.1B Crosstown LRT mega-contract comes in under estimates". Toronto Star. Archived from the original on November 5, 2015. Retrieved November 3, 2015.
  10. ^ "Next steps announced for Eglinton Crosstown West subway extension into Etobicoke, Mississauga". Global News. Archived from the original on August 19, 2020. Retrieved September 7, 2020.
  11. ^ "Tunnelling starts on the Eglinton Crosstown West Extension". Metrolinx. April 11, 2022. Archived from the original on April 12, 2022.
  12. ^ "Eglinton-Scarborough Crosstown Update" (PDF). Metrolinx. June 23, 2011. Archived from the original (PDF) on November 5, 2013. Retrieved July 28, 2011.
  13. ^ a b "Agenda Item History". app.toronto.ca. Archived from the original on March 17, 2016. Retrieved September 7, 2020.
  14. ^ "Eglinton Crosstown LRT will be delayed by about a year, source says". CBC Toronto. September 23, 2022. Archived from the original on September 25, 2022. Retrieved September 23, 2022.
  15. ^ "FAQs". Eglinton Crosstown: The Project. Metrolinx. Archived from the original on February 20, 2017. Retrieved February 12, 2017. Q: What is the timeline for the project? A:The project will be complete in 2021
  16. ^ Spurr, Ben (November 24, 2021). "Metrolinx agrees to new date to complete Crosstown LRT, says credit rating agency". Toronto Star. Archived from the original on November 25, 2021. Retrieved November 25, 2021.
  17. ^ Spurr, Ben (December 22, 2021). "Eglinton LRT to cost $325 million more — and won't open to riders until 2023". Toronto Star. Archived from the original on December 23, 2021. Retrieved December 23, 2021.
  18. ^ "Long-delayed Eglinton LRT delayed again, says Metrolinx". Toronto Star. September 22, 2022. Archived from the original on September 23, 2022. Retrieved September 23, 2022.
  19. ^ Ranger, Michael (May 16, 2023). "Eglinton Crosstown won't open until 2024, construction group to take legal action: Metrolinx". CityNews. Archived from the original on May 16, 2023. Retrieved May 16, 2023.
  20. ^ "Metrolinx refuses to say when long-delayed Eglinton Crosstown LRT might open". Toronto Star. September 27, 2023.
  21. ^ "Metrolinx CEO still unable to give an opening date for years-delayed Eglinton Crosstown LRT". Toronto Star. December 8, 2023.
  22. ^ a b "'There is a possibility': Eglinton Crosstown LRT could open this year, Ford government says". Toronto Star. December 2, 2025.
  23. ^ Smith, Mitchell (June 24, 1986). "Tonks makes pitch to keep Subway plan alive for Eglinton". Toronto Star. pp. A6.
  24. ^ Byers, Jim (April 5, 1990). "Huge transit expansion announced for Metro". Toronto Star. pp. A1.
  25. ^ Campion-Smith, Bruce (August 26, 1994). "Eglinton subway project under way $740 million line will create thousands of jobs, Rae pledges". Toronto Star. pp. A9.
  26. ^ Campion-Smith, Bruce (July 22, 1995). "Tories derail Eglinton subway". Toronto Star. pp. A4.
  27. ^ "TIMELINE: A brief history of Toronto's Eglinton Crosstown LRT project". Archived from the original on April 13, 2022. Retrieved April 29, 2022.
  28. ^ "Eglinton Crosstown Light Rail Transit stops and stations" (PDF). City of Toronto. November 2010. Archived from the original (PDF) on February 4, 2021. Retrieved July 30, 2011.
  29. ^ a b c "Eglinton Crosstown Backgrounder". Metrolinx. Archived from the original on August 3, 2020. Retrieved November 8, 2013.
  30. ^ "Document d'information – Eglinton Crosstown" (in French). Metrolinx. Archived from the original on November 7, 2019. Retrieved May 9, 2020.
  31. ^ Spears, John (August 9, 2008). "Distance between LRT stops criticized". Toronto Star. Archived from the original on August 12, 2008. Retrieved August 14, 2008.
  32. ^ "Eglinton Transit City line may survive". CBC News. January 4, 2011. Archived from the original on November 9, 2012. Retrieved April 24, 2011.
  33. ^ "Truncated version of Transit City does not satisfy mayor". East York Mirror. May 6, 2010. Archived from the original on May 28, 2021. Retrieved May 28, 2021.
  34. ^ D'Cruz, Andrew (December 1, 2010). "Mayor Rob Ford: "Transit City is over"". Toronto Life. Archived from the original on December 4, 2010. Retrieved August 4, 2014.
  35. ^ a b Kalinowski, Tess; Dale, Daniel (February 9, 2012). "Special transit meeting: Mayor Rob Ford dismisses council's vote against his subway plan". Toronto Star. Toronto. Archived from the original on February 10, 2012.
  36. ^ "Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Online Consultation". Eglington-Scarborough Crosstown. December 11, 2012. Archived from the original on December 16, 2012.
  37. ^ Kalinowski, Tess (May 12, 2013). "Metrolinx puts Leslie back on the Crosstown map". Toronto Star. Archived from the original on November 9, 2013. Retrieved November 8, 2013.
  38. ^ Kalinowski, Tess (May 6, 2013). "Scarborough councillors seek subway line instead of LRT: A group of Toronto councillors wants to replace the planned LRT for Scarborough with a subway. But a subway would cost $500 million more". Toronto Star. Archived from the original on May 9, 2013. Retrieved July 3, 2013. An LRT would use the same route as the SRT. It would be 9.9 kilometres (6.2 mi) versus 7.6 kilometres (4.7 mi) of subway. The LRT would have seven stations, the subway, only three.
  39. ^ Kalinowski, Tess (January 17, 2013). "TTC report threatens to reopen Scarborough subway debate: One commissioner says it's proof Scarborough can have a new subway line under construction within the decade, but Metrolinx dismisses that". Toronto Star. Archived from the original on September 26, 2013. Retrieved July 3, 2013. Glenn DeBaeremaeker (Ward 38, Scarborough Centre) said the latest TTC report gives him new confidence that there will be a subway underway in Scarborough within a decade.
  40. ^ a b Robinson, Jamie (May 10, 2013). "Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8)". Steve Munro. Retrieved November 2, 2017 – via email to Steve Munro. Metrolinx had identified some potential issues with the Brentcliffe Road launch site. ... We believed that our proposals would result in significant improvements to construction staging, schedule and traffic impacts. However, in discussions with the local community and with local community organizations it was clear that there was a strong preference for a stop at Leslie Street ...
  41. ^ Robinson, Jamie (June 17, 2013). "Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8)". Steve Munro. Retrieved November 2, 2017 – via email to Steve Munro. [One of the options recommended] included a continuation of the bored tunnel from the west to pass under the West Don River and portal east of the Don Valley Parkway. That option was selected because the cost differential with the at-grade options was minimal, provided that a station at Leslie Street was not required. If a Leslie Station would be required, then one of the at-grade south side options was the preferred option.
  42. ^ Kalinowski, Tess (February 12, 2013). "Eglinton-Crosstown LRT: Leasiders fight to put Leslie stop back on the map". Toronto Star. Retrieved October 11, 2014. The stop is being eliminated as part of a change to the LRT construction plan. Disappointed condo-dwellers at Leslie and Eglinton and, nearby Leaside are vowing to fight the decision by Metrolinx.
  43. ^ Landau, Jack (November 12, 2013). "Metrolinx Awards Contract for Crosstown LRT East Tunnel Section". UrbanToronto. Archived from the original on September 3, 2014. Retrieved October 12, 2014. With the winning bid for the eastern tunnel section announced, additional specific details about the Crosstown are now beginning to emerge. A newly released rendering from Metrolinx gives us our first look at the configuration of the future transition from tunneled section to surface track bed between Brentcliffe and Leslie.
  44. ^ Kalinowski, Tess (July 28, 2010). "Metrolinx orders tunneling machines". Toronto Star. Archived from the original on December 26, 2012. Retrieved September 3, 2017.
  45. ^ "Metrolinx purchases tunnel-boring machines for Eglinton Crosstown project". Railway Track and Structures. July 28, 2010. Retrieved February 16, 2026.
  46. ^ McKenzie, Daniel (August 17, 2016). "Big dig wraps for Eglinton Crosstown LRT". Toronto Sun. Archived from the original on August 19, 2016. Retrieved August 18, 2016.
  47. ^ "Announcing the winning names of the Tunnel Boring Machine Naming Contest... | Crosstown". thecrosstown.ca. Archived from the original on April 4, 2023. Retrieved February 10, 2026.
  48. ^ a b Leal, Brandon (June 5, 2013). "Eglinton Crosstown TBMs get a Personality and a Send-Off". Urban Toronto. Archived from the original on March 16, 2017. Retrieved February 12, 2017. In October 2012 Metrolinx announced a near month long contest public contest to name the tunnel boring machines (TBM).
  49. ^ "Metrolinx awards major tunnel-boring contract for light-rail expansion". Progressive Railroading. September 13, 2012. Retrieved February 16, 2026.
  50. ^ Menkes, Ashley (November 12, 2013). "Eglinton Crosstown LRT sees second, $177-million tunnelling contract awarded". National Post. Retrieved February 16, 2026.
  51. ^ a b "Request for Qualifications Issued for the Eglinton Crosstown LRT and Scarborough LRT Lines". Infrastructure Ontario. January 22, 2013. Archived from the original on October 5, 2013. Retrieved March 10, 2013.
  52. ^ "Toronto's Largest Transit Project Continues Moving Forward". Infrastructure Ontario. December 20, 2013. Retrieved February 16, 2026.
  53. ^ "Crosslinx Transit Solutions". Infrastructure Ontario. November 3, 2015. Retrieved February 16, 2026.
  54. ^ "Request for Proposals Stage Closed for Eglinton Crosstown LRT Project". Infrastructure Ontario. February 16, 215. Retrieved February 16, 2026.
  55. ^ "Crosslinx Transit Solutions Selected as Preferred Proponent for Eglinton Crosstown LRT Project". Infrastructure Ontario. June 8, 2015. Retrieved February 16, 2026.
  56. ^ Kalinowski, Tess (November 3, 2015). "$9.1B Crosstown LRT mega-contract comes in under estimates". Toronto Star. Archived from the original on November 5, 2015. Retrieved November 3, 2015.
  57. ^ "Contract Awarded for Eglinton Crosstown LRT". Infrastructure Ontario. Retrieved February 16, 2026.
  58. ^ a b Moore, Oliver (November 3, 2015). "Ontario government shaves $2-billion off Eglinton Crosstown LRT price tag". The Globe and Mail. Archived from the original on November 4, 2015. Retrieved November 3, 2015.
  59. ^ Barrow, Keith (November 4, 2015). "Eglinton Crosstown LRT contract signed". International Railway Journal. Retrieved February 16, 2026.
  60. ^ "Even More Light Rail in Toronto: The Eglinton Crosstown Line enters passenger service". Urban Transport Magazine. February 8, 2026. Retrieved February 16, 2026.
  61. ^ "Crosstown Community Update | Crosstown". Archived from the original on April 4, 2023. Retrieved April 4, 2023.
  62. ^ Thompson, John (March 8, 2016). "Eglinton Crosstown under way, underground". Railway Age. Archived from the original on February 1, 2021. Retrieved March 5, 2020.
  63. ^ Alcoba, Natalie (November 9, 2011). "Ford, McGuinty get up-close look at Eglinton LRT construction". National Post. Retrieved August 4, 2014.
  64. ^ Chu, Showwei (May 29, 2012). "Eglinton LRT unlikely to meet 2020 completion date: TTC report". Citytv News. Toronto. Retrieved June 25, 2012.}: CS1 maint: deprecated archival service (link)
  65. ^ Kalinowski, Tess (February 22, 2013). "Eglinton Crosstown LRT tunneling a step closer". Toronto Star. Archived from the original on November 5, 2013. Retrieved August 4, 2014.
  66. ^ "Machines begin tunnelling for Eglinton Crosstown LRT". CBC News. June 5, 2013. Archived from the original on July 19, 2013. Retrieved July 5, 2013.
  67. ^ a b Winsa, Patty (March 21, 2014). "Metrolinx begins its big eastern dig on the Eglinton Crosstown LRT: Get ready for traffic". Toronto Star. Archived from the original on March 23, 2014. Parts for the next two tunnel-boring machines to work on digging underground parts of the line — nicknamed Don and Humber — will arrive this summer and be assembled in the shaft, before they start drilling the 3.25-kilometre section west to Yonge St.
  68. ^ Alamenciak, Tim (April 30, 2014). "Eglinton Crosstown LRT back on schedule, engineer says". Toronto Star. Archived from the original on August 3, 2014. Retrieved January 22, 2015. "It's a seemingly simple process that's actually very high tech," said Kramer. The first of the two tunneling machines (dubbed Dennis) entered the ground June of 2013 and has made it to Caledonia Rd. from its starting point at Black Creek Dr. The other machine, Lea, is just behind.
  69. ^ Moore, Oliver (April 29, 2014). "Underground for now, construction proceeds on Eglinton LRT". The Globe and Mail. Archived from the original on December 21, 2014. Retrieved January 22, 2015. Headwalls that will form the box of the stations have been installed at Keele Street and Caledonia Road, and work is under way on one at Dufferin Street. The TBMs go right through headwalls after they have been built, in order to ensure a tight seal, and the two at work in this area are now on either side of what will eventually be the Caledonia LRT station.
  70. ^ Gupta, Rahul (May 9, 2014). "Eglinton LRT: Construction activity well underway on both sides of Allen Road". Inside Toronto. Archived from the original on January 23, 2015. Retrieved January 22, 2015. Digging 50 feet below street level, the 81-metre long TBMs nicknamed Dennis and Lea are located in the vicinity of Caledonia Road, one of 12 underground Crosstown stations planned for the route. They are expected to reach the Allen later this year, when they will be redeployed beyond Eglinton West subway station to continue the dig east towards Yonge Street.
  71. ^ "TBM tracker". Google My Maps. Archived from the original on May 16, 2023. Retrieved May 16, 2023.
  72. ^ Carville, Olivia (April 19, 2015). "An exciting glimpse at boring machines on Eglinton". Toronto Star. Archived from the original on December 8, 2017. Retrieved September 3, 2017.
  73. ^ Pelley, Lauren (April 19, 2015). "Eglinton businesses feeling sting of Crosstown construction". Toronto Star. Archived from the original on January 9, 2019. Retrieved September 3, 2017.
  74. ^ Kalinowski, Tess (September 24, 2015). "Eglinton Crosstown to open a year later than expected". Toronto Star. Archived from the original on September 25, 2015. Retrieved September 24, 2015.
  75. ^ "Launch of tunnel boring machines and tunnelling work in the east". Metrolinx. October 1, 2015. Retrieved October 13, 2015.
  76. ^ "Temporary Closure of Holly Street at Eglinton Avenue East". Metrolinx. February 24, 2016. Archived from the original on January 3, 2017. Retrieved February 12, 2017. The extraction shaft is required to be completed in advance of receiving the two TBMs (Don and Humber), which are currently tunnelling westward from their start-point, just east of Brentcliffe Road.
  77. ^ "Crosstown Tunnelling Reaches Yonge Street". Ministry of Transportation of Ontario. May 10, 2016. Archived from the original on September 18, 2016. Retrieved February 12, 2017. Today Tunnel Boring Machines (TBMs) Dennis and Lea, boring the western segment tunnels, arrived at Yonge Street having travelled 6,419 metres from where they started at Black Creek Drive in spring 2013.
  78. ^ a b McKenzie, Daniel (August 17, 2016). "Big dig wraps for Eglinton Crosstown LRT". Toronto Sun. Archived from the original on August 19, 2016. Retrieved August 18, 2016.
  79. ^ "Eglinton Crosstown LRT tunnelling completed in Toronto". Railway Gazette International. August 18, 2016. Retrieved February 16, 2026.
  80. ^ "Join us March 13 to say farewell to the Crosstown's TBM". Metrolinx. October 3, 2017. Retrieved March 13, 2017. Metrolinx invites you to join us throughout the week of March 13, 2017 to watch the pieces of being lifted and transported offsite. We will start the process of extracting the tunnel boring machines (TBM) from the completed east tunnels, and say farewell to our faithful helpers, TBM Don and TBM Humber. The TBMs will be disassembled and lifted from extraction shaft just east of Yonge & Eglinton in four oversized sections over four days. ... Each piece will be lifted from the extraction shaft in the morning, and placed on the ground within the construction zone. Later, after 9 p.m. that night, the piece will be loaded onto a large truck and hauled away. TBM Don, the machine that bored the north tunnel, will be removed first.
  81. ^ Dolski, Megan (March 13, 2017). "Work starts on stations, tracks for Eglinton-Crosstown LRT". Toronto Star. Archived from the original on March 14, 2017. Retrieved March 14, 2017.
  82. ^ "Eglinton Crosstown Update". Metrolinx. March 13, 2020. Archived from the original on March 16, 2020. Retrieved March 16, 2020.
  83. ^ "Crews break ground on 1st of 25 Eglinton Crosstown stations". CBC News. March 10, 2016. Archived from the original on March 15, 2016. Retrieved March 22, 2016.
  84. ^ Johnston, Paul (April 18, 2016). "Eglinton scaffolding collapse injures 7, including baby: paramedics". CP24. Archived from the original on December 31, 2017. Retrieved February 11, 2020.
  85. ^ a b "Eglinton Crosstown LRT Updates – August 2017". Metrolinx. August 11, 2017. Archived from the original on April 22, 2022. Retrieved August 11, 2017.
  86. ^ "Eglinton Crosstown LRT Updates – July 2017". Metrolinx. July 14, 2017. Archived from the original on April 30, 2021. Retrieved July 14, 2017.
  87. ^ a b "Eglinton Crosstown Update". Metrolinx. January 11, 2019. Archived from the original on April 7, 2022. Retrieved January 13, 2019.
  88. ^ "Bombardier delivers first LRV for Eglinton Crosstown, on track for TTC streetcar delivery". CityNews. January 8, 2019. Archived from the original on January 9, 2019. Retrieved January 8, 2019.
  89. ^ "East Guideway Concrete Pour". Metrolinx. February 15, 2019. Archived from the original on December 21, 2021. Retrieved April 7, 2019.
  90. ^ a b "Eglinton Crosstown LRT could be $330 million over budget and open seven months late, internal documents warn | The Star". thestar.com. December 30, 2019. Archived from the original on March 14, 2020. Retrieved February 19, 2020.
  91. ^ @GreggLintern (December 14, 2019). "Light rail at the end of the tunnel" (Tweet) – via Twitter.
  92. ^ "Training tale – First Eglinton Crosstown light rail vehicle hits tracks of main Toronto line". Metrolinx. January 9, 2020. Archived from the original on December 27, 2019. Retrieved December 20, 2019.
  93. ^ "Eglinton Crosstown Update February 2020". Metrolinx. February 2020. Archived from the original on February 21, 2020. Retrieved February 21, 2020.
  94. ^ "Eglinton Crosstown LRT won't be ready until 'well into 2022,' Metrolinx says". CBC News. February 18, 2020. Archived from the original on February 18, 2020. Retrieved February 18, 2020.
  95. ^ Spurr, Ben (February 17, 2020). "Eglinton Crosstown faces another setback, delayed until 2022". Toronto Star. Archived from the original on February 18, 2020. Retrieved February 18, 2020.
  96. ^ Rider, David (March 9, 2020). "Ford government pledges $3M for businesses affected by Eglinton LRT construction". Toronto Star. Archived from the original on March 10, 2020. Retrieved March 10, 2020.
  97. ^ "Eglinton Crosstown Update". Metrolinx. March 13, 2020. Archived from the original on March 16, 2020. Retrieved March 16, 2020.
  98. ^ "See video of the first time a light rail vehicle passes through a Crosstown tunnel". Metrolinx. May 4, 2020. Archived from the original on May 9, 2020. Retrieved May 9, 2020.
  99. ^ Spurr, Ben (October 1, 2020). "New report says the Eglinton Crosstown LRT could open five months late — and without its Eglinton stop". Toronto Star. Archived from the original on October 2, 2020. Retrieved October 1, 2020.
  100. ^ "In 'extraordinary step,' company building Eglinton Crosstown hits province with lawsuit". Canadian Broadcasting Corporation. October 8, 2020. Archived from the original on October 10, 2020. Retrieved October 8, 2020.
  101. ^ "The art of the line – How Toronto's Crosstown LRT is adding creative touches to transit design". December 9, 2020. Archived from the original on December 11, 2020. Retrieved December 11, 2020.
  102. ^ "Crosstown projects sees new track brought in for light rail vehicles". Metrolinx. April 29, 2021. Archived from the original on April 29, 2021. Retrieved April 29, 2021.
  103. ^ "Crosstown LRT projects sees significant concrete milestones as well as main entrance features at Science Centre Station". Metrolinx. April 21, 2021. Archived from the original on April 21, 2021. Retrieved April 21, 2021.
  104. ^ "Overhead Catenary System Energization between Laird Drive and Kennedy Road". Metrolinx. May 3, 2021. Archived from the original on May 1, 2021. Retrieved May 1, 2021.
  105. ^ "Powering up the Eglinton Crosstown LRT for the first time". Metrolinx. May 10, 2021. Retrieved May 10, 2021.}: CS1 maint: deprecated archival service (link)
  106. ^ Spurr, Ben (May 17, 2021). "Eglinton Crosstown LRT to cost more and take longer, after builder scores legal victory". Toronto Star. Archived from the original on May 17, 2021. Retrieved May 18, 2021.
  107. ^ "See new videos of Crosstown light rail vehicles arrive in preparation for testing to come". Metrolinx. June 3, 2021. Archived from the original on June 3, 2021. Retrieved June 8, 2021.
  108. ^ "Testing begins as Crosstown LRT vehicles make their first move along Eglinton Avenue". Metrolinx. August 24, 2021. Archived from the original on August 28, 2021. Retrieved August 28, 2021.
  109. ^ "Final pieces of trackwork being installed at Eglinton Station for Crosstown LRT project". Metrolinx. October 5, 2021. Archived from the original on October 5, 2021.
  110. ^ "Crews install last piece of track for Eglinton Crosstown LRT". Metrolinx. November 2, 2021. Archived from the original on November 2, 2021.
  111. ^ "See video as first Crosstown light rail vehicles travel from Laird Station back to their storage facility". Metrolinx. November 18, 2021.}: CS1 maint: deprecated archival service (link)
  112. ^ Spurr, Ben (December 22, 2021). "Eglinton LRT to cost $325 million more — and won't open to riders until 2023". Toronto Star. Archived from the original on December 23, 2021. Retrieved December 23, 2021.
  113. ^ "Not just any red light – Final Eglinton Crosstown LRT signal installed at Laird Station". Metrolinx. February 24, 2022. Archived from the original on February 24, 2022.
  114. ^ "All of Toronto's Crosstown vehicles are ready to go as the line actually nears completion". www.blogto.com. Archived from the original on April 1, 2022. Retrieved April 1, 2022.
  115. ^ "Full-length vehicle testing starts for Eglinton Crosstown – plus station updates". Metrolinx. July 21, 2022. Archived from the original on July 21, 2022.
  116. ^ "Long-delayed Eglinton LRT delayed again, says Metrolinx". Toronto Star. September 22, 2022. Archived from the original on September 23, 2022. Retrieved September 23, 2022.
  117. ^ "Eglinton Crosstown LRT will be delayed by about a year, source says". CBC Toronto. September 23, 2022. Archived from the original on September 25, 2022. Retrieved September 23, 2022.
  118. ^ a b "No 'credible plan' for completion of Eglinton LRT, says Metrolinx". Toronto Star. December 12, 2022. Archived from the original on December 9, 2022. Retrieved December 9, 2022.
  119. ^ "'Something really stinks here': Why you still don't know when the Eglinton LRT will start running". Toronto Star. April 22, 2023. Archived from the original on April 22, 2023. Retrieved April 22, 2023.
  120. ^ "Never-used Eglinton Crosstown LRT station platform ripped up due to uneven concrete". CityNews. April 24, 2023. Archived from the original on April 25, 2023.
  121. ^ Lilley, Brian (April 26, 2023). "Eglinton Crosstown won't open until 2024 — at the earliest". Toronto Sun. Archived from the original on May 18, 2023. Retrieved April 28, 2023.
  122. ^ "Metrolinx CEO sheds light on reasons for Eglinton LRT delays". Toronto Star. April 27, 2023. Archived from the original on April 28, 2023. Retrieved April 28, 2023.
  123. ^ "Upcoming TTC subway closures and weekend diversions". Toronto Transit Commission. May 11, 2023. Archived from the original on May 12, 2023.
  124. ^ Ranger, Michael (May 16, 2023). "Eglinton Crosstown won't open until 2024, construction group to take legal action: Metrolinx". CityNews. Archived from the original on May 16, 2023. Retrieved May 16, 2023.
  125. ^ a b c "Metrolinx CEO still unable to give an opening date for years-delayed Eglinton Crosstown LRT". Toronto Star. December 8, 2023.
  126. ^ a b "Metrolinx refuses to say when long-delayed Eglinton Crosstown LRT might open". Toronto Star. September 27, 2023.
  127. ^ "TTC budget plans on Eglinton Crosstown and Finch West LRTs opening in the fall". Toronto Star. December 15, 2023.
  128. ^ "'Major construction' complete on Eglinton Crosstown but software and quality assurance issues outstanding: Metrolinx". CTV News. March 25, 2024.
  129. ^ a b "Report sheds light on beleaguered Eglinton Crosstown LRT's progress". Toronto Star. July 8, 2024.
  130. ^ "'Unacceptable': Toronto councillor calls for public inquiry into Eglinton Crosstown delays". CablePulse 24. October 5, 2024.
  131. ^ "Eglinton Crosstown will open no earlier than mid-2025, TTC chair says". CBC News. December 4, 2024.
  132. ^ Takagi, Andy (March 13, 2025). "Eglinton Crosstown LRT finally has an opening date, according to sources". Toronto Star. Archived from the original on March 13, 2025. Retrieved March 14, 2025.
  133. ^ Draaisma, Muriel (June 4, 2025). "Ford says Eglinton Crosstown LRT still on track to open in September 2025". msn.ca. Retrieved June 5, 2025.
  134. ^ a b c Colin, D'Mello (March 28, 2025). "Metrolinx renaming Eglinton Crosstown LRT's Ontario Science Centre station". Global News. Retrieved March 28, 2025.
  135. ^ "Major milestones: Here's what needs to happen before the Eglinton Crosstown can open". CTV News. June 17, 2025. Archived from the original on June 17, 2025.
  136. ^ Alevato, Julia (July 17, 2025). "Bad news, commuters: The Eglinton Crosstown LRT may be delayed again". CBC News. Retrieved July 18, 2025.
  137. ^ "Eglinton Crosstown LRT vehicle "availability and reliability" latest issue to face line before launch". CityNews. August 6, 2025.
  138. ^ Takagi, Andy (October 8, 2025). "Eglinton Crosstown LRT begins final 30-day testing phase — but still no opening date". Toronto Star.
  139. ^ "Ontario Achieves Substantial Completion of Eglinton Crosstown LRT". news.ontario.ca. December 5, 2025. Retrieved February 16, 2026.
  140. ^ "Toronto city council votes to speed up Finch West LRT". Toronto Star. December 16, 2025.
  141. ^ "Behind the scenes, Eglinton Crosstown LRT brake issues caused confusion, disagreement between Metrolinx and the TTC". Toronto Star. January 31, 2026.
  142. ^ Thayaparan, Arrthy (February 8, 2026). "Beautiful, wonderful, or Toronto transit's black eye? Whatever it is, the Eglinton Crosstown is finally open". CBC News. Archived from the original on February 9, 2026. Retrieved February 9, 2026.
  143. ^ "TTC to begin phased start to service on Line 5 Eglinton". Toronto Transit Commission. February 3, 2026. Archived from the original on February 4, 2026.
  144. ^ "Eglinton Crosstown LRT to open Sunday with reduced service, muted celebrations". Toronto Star. February 3, 2026.
  145. ^ "City of Toronto: Get Involved > Eglinton Crosstown Light Rail Transit (LRT) > Frequently Asked Questions > Stations and Stops". City of Toronto. August 20, 2011. Archived from the original on October 21, 2011. Retrieved October 24, 2011.
  146. ^ Mackenzie, Robert (March 17, 2020). "Metrolinx's Eglinton West LRT Business Case Goes Underground". UrbanToronto. Archived from the original on December 3, 2020. Retrieved September 21, 2020.
  147. ^ "Science Centre Station and West At-Grade (Sunnybrook Park Stop to O'Connor Stop) Open House". Metrolinx. November 14, 2017. p. 29. Archived from the original on November 16, 2017. Retrieved November 14, 2017.
  148. ^ "Crosstown projects sees new track brought in for light rail vehicles". Metrolinx. April 29, 2021. Archived from the original on April 29, 2021. Retrieved April 29, 2021.
  149. ^ Spurr, Ben (April 29, 2018). "Underground Eglinton Crosstown LRT stations take shape with unique mining technique". Toronto Star. Retrieved April 30, 2018.
  150. ^ "Sunnybrook Park stop is more light in Crosstown progress". Metrolinx. May 6, 2019. Archived from the original on May 9, 2019. Retrieved May 14, 2019.
  151. ^ a b "Transit Facts – Surface Section" (PDF). Metrolinx. Archived from the original (PDF) on May 9, 2020. Retrieved May 9, 2020.
  152. ^ "The Eglinton Crosstown LRT is going green". Metrolinx. August 4, 2021. Archived from the original on August 31, 2021. Retrieved August 30, 2021.
  153. ^ "Stations and Stops". Metrolinx. Archived from the original on January 14, 2018. Retrieved January 10, 2018.
  154. ^ a b c Kalinowski, Tess (November 24, 2015). "Eglinton West station to become 'Cedarvale' because of Crosstown LRT". Toronto Star. Archived from the original on November 24, 2015. Retrieved November 24, 2015.
  155. ^ "Line 6 Finch West to open on December 7". Toronto Transit Commission. November 24, 2025. Retrieved November 24, 2025. The opening of Line 6 also means the names of two existing TTC stations will officially change on December 7. Eglinton West Station will become Cedarvale Station, while Dundas Station will become TMU Station. These changes mean Line 1 trains will now announce arrival at the stations with their new names
  156. ^ "Leslie Stop". The Crosstown.ca. January 14, 2017. Archived from the original on October 8, 2014. Retrieved November 4, 2017.
  157. ^ a b "Aga Khan & Eglinton". Metrolinx. Archived from the original on September 18, 2020. Retrieved November 3, 2017.
  158. ^ "Wynford Stop". Eglinton Crosstown. February 27, 2017. Retrieved November 4, 2017.
  159. ^ "Bermondsey Stop". Eglinton Crosstown. January 14, 2016. Retrieved November 4, 2017.
  160. ^ "Victoria Park Stop". Eglinton Crosstown. May 11, 2018. Retrieved April 28, 2020.
  161. ^ "Pharmacy Stop". Eglinton Crosstown. May 10, 2018. Retrieved April 28, 2020.
  162. ^ "Lebovic Stop". Eglinton Crosstown. December 3, 2015. Retrieved November 6, 2017.
  163. ^ "Golden Mile (formerly Warden) Stop". Eglinton Crosstown. January 14, 2016. Retrieved November 6, 2017.
  164. ^ "Birchmount Stop". Eglinton Crosstown. December 3, 2015. Retrieved November 7, 2017.
  165. ^ "Ionview Stop". Eglinton Crosstown. Metrolinx. December 5, 2015. Retrieved November 7, 2017.
  166. ^ "Eglinton Crosstown Line Station and Stop Names". Metrolinx. October 2, 2015. Archived from the original on October 21, 2020. Retrieved October 2, 2015.
  167. ^ "Ferrand Stop". Eglinton Crosstown. February 27, 2017. Archived from the original on November 7, 2017. Retrieved November 3, 2017.
  168. ^ Kalinowski, Tess (January 15, 2016). "Eglinton Crosstown station name sparks contentious Metrolinx debate". Toronto Star. Retrieved January 15, 2016.
  169. ^ "Line 5 Eglinton Station Names" (PDF). Board Presentation. Toronto Transit Commission. November 23, 2015. Archived from the original (PDF) on August 31, 2021. Retrieved November 30, 2015. In order to reduce confusion with Eglinton Station and Line 5 Eglinton, Eglinton West Station will be renamed. ... TTC staff evaluated the initial report and the proposed names and provided feedback and recommendations. A primary TTC concern was to avoid replication and redundancy with existing TTC station names. The proposed names are unique and are not likely to be confused with existing station names.
  170. ^ Colin, D'Mello (April 20, 2023). "Ford government to rename Science Centre subway station in Toronto". Global News. Retrieved April 20, 2023.
  171. ^ Benzie, Robert; Ferguson, Rob (June 21, 2024). "Ford government closing Ontario Science Centre today after report found roof in danger of collapsing". Toronto Star. Retrieved June 21, 2024.
  172. ^ a b c d Bozikovic, Alex (February 8, 2026). "Will the Eglinton Crosstown carry Toronto forward?". The Globe and Mail. Retrieved February 16, 2026.
  173. ^ Lestage, Daoust. "Eglinton Crosstown LRT – Design excellence – Daoust Lestage". Retrieved February 22, 2026. Daoust Lestage inc. (Fairbank Station)
    DIALOG and Arcadis (Forest Hill, Chaplin and Avenue Stations)
    Arcadis (Mount Dennis, Keelesdale, Oakwood, Eglinton, Leaside, Laird, Science Centre and Kennedy Stations and At-grade Stops)
    NORR (Caledonia, Cedarvale and Mount Pleasant Stations)
  174. ^ a b c Novakovic, Stefan (November 22, 2024). "The Big Move: A Preview of Toronto's Eglinton Crosstown LRT". Azure Magazine. Retrieved February 22, 2026.
  175. ^ "Full-scale replica shows off Eglinton Crosstown station design". Metrolinx. June 19, 2018. Retrieved February 22, 2026.
  176. ^ Metrolinx. Line 5 Eglinton station tours (Video). YouTube. Retrieved February 24, 2026.
  177. ^ Bozikovic, Alex [@alexbozikovic]; (February 14, 2026). "It's rare to witness the opening of a major urban transit line. The Eglinton Crosstown is, in architectural terms, a modest success despite its troubled beginnings. Heartening to see a public project aim high and move forward. Art shown by @sarahmorris and @douglascoupland" – via Instagram.
  178. ^ "McDonalds to be demolished for Bayview LRT". Bayview News. November 7, 2013. Retrieved October 21, 2015. A nice bit of news on the northwest corner of Mt Pleasant and Eglinton where, according to Metrolinx information, the facade of the old building will be retained.
  179. ^ "Onetime Kodak building to move 60 metres for new LRT station". CBC News. February 25, 2016.
  180. ^ Graziani, Téana (July 6, 2022). "Art Installations Underway at Crosstown Line 5 Stations". urbantoronto.ca. Retrieved February 19, 2026.
  181. ^ a b Spurr, Ben (January 15, 2018). "Art installations will enliven Eglinton Crosstown LRT". Toronto Star. Archived from the original on January 18, 2018. Retrieved January 18, 2018.
  182. ^ "New art installations going up at Eglinton Crosstown LRT station". Metrolinx. June 30, 2022. Retrieved February 19, 2026.
  183. ^ a b "How will the Eglinton Crosstown LRT's automatic train control work? We break down every major element in an infographic". Metrolinx News. Metrolinx. December 9, 2019. Archived from the original on January 9, 2020. Retrieved January 9, 2020.
  184. ^ Munro, Steve (June 17, 2013). "Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8)". Steve Munro. Archived from the original on March 4, 2015. Retrieved June 17, 2013.
  185. ^ "Light Rail Transit Facts". Metrolinx. May 31, 2015. Archived from the original on May 16, 2015. Retrieved May 31, 2015.
  186. ^ "Eglinton Crosstown Environmental Report" (PDF). TTC/City Of Toronto. March 2010. Archived (PDF) from the original on May 26, 2021. Retrieved April 8, 2019.
  187. ^ Spurr, Ben (July 20, 2016). "Metrolinx threatens legal action over late delivery of light rail vehicles". Toronto Star. Archived from the original on July 20, 2016. Retrieved July 20, 2016.
  188. ^ Spurr, Ben; Pagliaro, Jennifer (October 31, 2016). "Report outlines steep costs of running new Toronto transit lines". Toronto Star. Archived from the original on November 1, 2016. Retrieved October 31, 2016.
  189. ^ "Eglinton Crosstown LRT Updates – July 2017". Metrolinx. July 14, 2017. Archived from the original on April 30, 2021. Retrieved July 14, 2017.
  190. ^ "Metrolinx enhances platform safety on Eglinton Crosstown LRT". Metrolinx. May 31, 2022. Archived from the original on June 1, 2022.
  191. ^ "Transit City measures up to international standard". Toronto Star. January 6, 2010. Archived from the original on October 19, 2012. Retrieved October 4, 2014.
  192. ^ Bow, James (June 13, 2019). "The Toronto Flexity Freedom Light Rail Vehicles". Transit Toronto. Retrieved February 22, 2020.
  193. ^ Spurr, Ben (March 2, 2017). "Metrolinx in talks with another company to replace Bombardier vehicles as fears mount over $500,000 a day late fees". Toronto Star. Archived from the original on April 10, 2017. Retrieved May 12, 2017.
  194. ^ Spurr, Ben (May 12, 2017). "Province had no choice but to seek Bombardier substitute for Eglinton LRT: Del Duca". Toronto Star. Archived from the original on May 12, 2017. Retrieved May 12, 2017.
  195. ^ "Metrolinx statement on Alstom/Bombardier". Metrolinx. Archived from the original on September 22, 2022. Retrieved May 12, 2017.
  196. ^ Spurr, Ben (May 13, 2017). "How do TTC's streetcar options compare? It's Bombardier versus Alstom". Toronto Star. Archived from the original on June 12, 2018. Retrieved May 13, 2017.
  197. ^ Spurr, Ben (October 30, 2018). "First Eglinton Crosstown LRT vehicle to be ready in November, Bombardier says". Toronto Star. Archived from the original on October 31, 2018. Retrieved October 30, 2018. The company plans to ship the vehicle to Toronto next month, and has a target of delivering five more by mid-February. It intends to supply the entire fleet of 76 vehicles to Metrolinx, the provincial agency that's building the Crosstown, in time for the line's opening.
  198. ^ "Bombardier delivers first LRV for Eglinton Crosstown, on track for TTC streetcar delivery". CityNews. January 8, 2019. Archived from the original on January 9, 2019. Retrieved January 8, 2019.
  199. ^ "Training tale – First Eglinton Crosstown light rail vehicle hits tracks of main Toronto line". Metrolinx. January 9, 2020. Archived from the original on December 27, 2019. Retrieved December 20, 2019.
  200. ^ "Keele Street to Jane Section and Black Creek Maintenance & Storage Facility Environmental Project Report Addendum Online Consultation". Metrolinx. 2016. Archived from the original on July 25, 2016. Ultimate storage yard capacity of 162 vehicles;
  201. ^ Lorinc, John (November 23, 2012). "Down (but not out) Mount Dennis area pins hopes on Metrolinx". The Globe and Mail. Archived from the original on March 4, 2016. Retrieved March 28, 2013. A sprawling storage and maintenance facility for the light-rail vehicles will be built on the Kodak site within a few years.
  202. ^ Munro, Steve (February 17, 2010). "Eglinton LRT: Trouble Brewing in Mt. Dennis (Update 2)". Archived from the original on March 4, 2015. Some speakers addressed the use of the Kodak lands for the proposed carhouse, and asked that alternative schemes be considered. Part of this relates to a proposed "big box" development on the land. However, Council approved the acquisition of this property, by expropriation if necessary, in December.
  203. ^ Kalinowski, Tess (February 16, 2010). "Residents ask TTC for LRT tunnel through Mount Dennis". Toronto Star. Archived from the original on October 3, 2013. In addition to the $4.6 billion the province has committed to the Eglinton LRT, the centrepiece of Toronto's Transit City plan, the TTC also wants to build a carhouse on the old Kodak lands in Mount Dennis.
  204. ^ "New green energy facility is powering up the Eglinton Crosstown LRT". Metrolinx. July 31, 2019. Retrieved October 27, 2019.
  205. ^ "Eglinton Crosstown West Extension". www.metrolinx.com. Retrieved February 17, 2026.
  206. ^ Hope, Andrew (February 12, 2026). "CPG (Rapid Transit) State of the Network" (PDF). Metrolinx.
  207. ^ "Progress updates". Pearson Airport. Archived from the original on March 11, 2024. Retrieved March 11, 2024. We're continuing to work with Metrolinx and all levels of government to advance planning and design for the proposed connection of the Eglinton Crosstown West Extension to Toronto Pearson.
  208. ^ a b c "Advancing City Priority Transit Expansion Projects – Eglinton East LRT and Waterfront East LRT" (PDF). City of Toronto. May 25, 2022. Archived (PDF) from the original on June 1, 2022.
  209. ^ "Transit Network Expansion Update" (PDF). Toronto Transit Commission. July 14, 2022. Archived (PDF) from the original on July 9, 2022.
[edit]