Chennai Metro

Chennai Metro
A metro train at Guindy station on the Blue Line
A metro train at Guindy station on the Blue Line
Map of Chennai's urban rail network with operational, under-construction and planned lines
Map of Chennai's urban rail network with operational, under-construction and planned lines
Overview
OwnerChennai Metro Rail Limited
LocaleChennai, Tamil Nadu, India
Transit typeRapid transit
Number of lines2 (operational)
3 (under construction)
Line numberOperational
Number of stations41
Annual ridership105.24 million (2024)[1]
Key peopleKatikithala Srinivas, IAS (Chairman)
M.A. Siddique, IAS (Managing Director)
HeadquartersMetroS, Anna Salai, Nandanam, Chennai
Websitechennaimetrorail.org
Operation
Began operation29 June 2015; 10 years ago (2015-06-29)
Operator(s)Chennai Metro Rail Limited
Number of vehicles52
Train length100 m (330 ft)
Headway6–12 minutes
Technical
System length54.1 km (33.6 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification25 kV 50 Hz AC overhead line[2]
Top speed120 km/h (75 mph)

The Chennai Metro is a rapid transit system serving the city of Chennai, India. It is operated by Chennai Metro Rail Limited, a joint venture between the Government of India and the Government of Tamil Nadu. As of December 2025, the network consists of two operational lines spanning 54.1 km (33.6 mi) and has 41 underground and elevated stations. The system runs on standard gauge and is powered by 25 kV 50 Hz AC overhead electric lines.

Plans for a metro rail system for Chennai started in 2007–08 with construction commencing in February 2009. Test runs began in 2014, and the first segment of the metro between the Alandur and Koyambedu stations on the Green Line began operations on 29 June 2015. On 21 September 2016, operations on the Blue Line commenced between Chennai Airport and Little Mount. The underground stretch from AG-DMS to Washermanpet of the Blue Line opened on 10 February 2019, completing the first phase.

As a part of the second phase, three more lines covering a length of 118.9 km (73.9 mi) are planned and are under construction. The Chennai Mass Rapid Transit System (MRTS), operated by the Indian Railways, is planned to be incorporated into the Chennai Metro. A light rail has been proposed to connect Tambaram on the Chennai suburban rail network with Velachery on the MRTS. Further extensions are also planned for the three lines under construction.

Background

[edit]

A single electrified line from Chennai Beach to Tambaram began operations in 1931 as part of the Chennai Suburban Railway. Two other rail lines were subsequently built, connecting Chennai Central to Gummidipoondi and Tiruvallur in 1979.[3][4] In 1965, the Planning Commission evaluated the capacity of the transportation network in major metropolitan cities including Madras, and developed plans for further expansion of transportation amenities.[5][6] As a result, an initial stretch of the Chennai Mass Rapid Transit System (MRTS) between Chennai Beach and Chepauk opened in 1995 – the first elevated rail line in India. The MRTS later extended to Thirumayilai in 1997, to Thiruvanmiyur in 2004, and to Velachery in 2007.[7][8][9] In 2006, a modern metro rail system for Chennai was planned, to be modeled after the Delhi Metro.[10][11]

Planning and construction

[edit]

Phase I

[edit]
Chennai Metro - Phase I
Phase I
North Line
Wimco Nagar Depot
Wimco Nagar
Tiruvottriyur
Tiruvottriyur Theradi
Kaladipet
Tollgate
New Washermanpet
Tondiarpet
Sir Theagaraya College
Washermanpet
Basin Bridge
Mannadi
Chennai Central and MMC
High Court
Chennai Central
Egmore
Nehru Park
Kilpauk Medical College
Government Estate
Pachaiyappa's College
Shenoy Nagar
LIC
Anna Nagar East
Anna Nagar Tower
Thousand Lights
Red Line Thirumangalam
AG – DMS
Koyambedu Depot
Teynampet
Red Line Koyambedu
Nandanam
CMBT CMBT
Saidapet
Arumbakkam
Little Mount
Vadapalani
Ashok Nagar
Guindy
Ekkattuthangal
Red Line Alandur
Nanganallur Road
St. Thomas Mount Red Line
Meenambakkam
Chennai Airport
Tirusulam
Pallavaram
Pallavaram
Kothandam Nagar
Chromepet
Chromepet
Mahalakshmi Colony
Thiru.Vi.Ka Nagar
Bus interchange Tambaram
Tambaram
Irumbuliyur
Peerkankaranai
Perungalathur
Perungalathur
Vandalur
Vandalur
Arignar Anna Zoological Park
Kilambakkam
Kilambakkam bus terminus, Chennai Kilambakkam

Collapsible section not closed properly!

The Delhi Metro Rail Corporation was tasked to prepare a project report for the implementation of a metro rail system in Chennai.[11] The Government of Tamil Nadu approved the first phase of the project in November 2007.[12] The first phase was planned with two lines covering 45.1 km (28.0 mi) with 25 km (16 mi) being underground. The first corridor would connect Washermanpet with Chennai International Airport extending for 23.1 km (14.4 mi) with 14.3 km (8.9 mi) being underground and the second corridor would connect St.Thomas Mount with Chennai Central extending for 22 km (14 mi) with 9.7 km (6.0 mi) being underground.[11] In December 2007, the Chennai Metro Rail Limited (CMRL) was established as a joint venture between the union and state governments to execute the project.[12] The Planning commission gave an in-principle approval for the project in April 2008 with the final approval by the Union Council of Ministers in January 2009.[12][13] The estimated base cost of the first phase was 146 billion (US$1.7 billion) of which 59% was loaned by Japan International Cooperation Agency (JICA). The Government of India contributed 15% of the cost and the Government of Tamil Nadu financed the remaining 21% of the project.[11]

In February 2009, a 1.99 billion (US$24 million) contract was awarded for the construction of a 4.5 km (2.8 mi) long viaduct along the Inner Ring Road between Koyambedu and Ashok Nagar and the construction started on 10 June.[14][15] In March 2009, a US$30 million contract was awarded to a consortium of five companies headed by French company Egis for technical consultancy on the project.[16] In August 2010, the contract for supplying rolling stock was awarded to Alstom for US$243 million.[17][18] In January 2011, a joint venture between Larsen & Toubro (L&T) and Alstom was awarded the a 4.49 billion (US$53 million) contract for design and construction of tracks and a depot at Koyambedu.[19][20]

Construction of an elevated section in the first phase in 2011

Contracts for the construction of underground sections of the first phase were awarded to Gammon India and Mosmetrostroy in February 2011.[21][22] In June 2011, the contract for the construction of the ten elevated stations of the first phase was awarded to Consolidated Construction Consortium.[23][24] The contract for the supply of lifts and escalators was awarded to a joint venture of Johnson Lifts and SJEC Corporation.[25] The contract for power supply and overhead electrification was awarded to Siemens for 3.05 billion (US$36 million) and contracts for automatic fare collection, tunnel ventilation, and air conditioning were awarded to Nippon Signal, Emirates Trading Agency, and Voltas respectively.[26][27][28] In July 2012, the first tunnel boring machine was launched and by October that year, eleven machines were operated by three consortia–Afcons-Transtonnelstroy, L&T and SUCG.[29]

In August 2012, a construction worker was killed and six others were seriously injured after a crane failed and crashed at an under construction site near Pachaiyappa's College and on 10 January 2013, a 22-year-old construction worker was killed and three others were injured at a construction site between Alandur and St. Thomas Mount.[30] On 6 November 2013, a test run was conducted along a stretch of 1 km (0.62 mi) track.[31] The project faced several delays and missed deadlines due to problems with land acquisition and cancellation of construction contracts.[32][33] On 11 January 2014, a crane toppled over, killing a 20-year-old construction worker and seriously injuring another at Saidapet.[34]

Chennai Metro during trials in early 2014

On 14 February 2014, the maiden trial run was conducted between Koyambedu and Ashok Nagar stations.[35][36] The metro received the statutory speed certification clearance from the Research Design and Standards Organisation in August that year.[37][38] In January 2015, a report was submitted to the Commissioner of Metro Rail Safety (CMRS) for mandatory safety approvals.[39] After inspecting the infrastructure, the CMRS submitted the report to the Railway Board in April 2015.[40][41][42]

Elevated track over the Adyar river

Operations on the Green Line between the Alandur and Koyambedu stations commenced on 29 June 2015.[43] The Blue Line segment from the Airport and Little Mount stations commenced operations on 21 September 2016.[44] The first underground section between Thirumangalam to Nehru Park on the Green Line opened on 14 May 2017,[45] and the extension to Chennai central was completed on 25 May 2018 along with the section from the Saidapet and AG-DMS stations on the blue line.[46] On 10 February 2019, the underground stretch from AG-DMS to Washermanpet of Blue Line was opened, marking the completion of the first phase of the metro.[47]

Chennai Metro - Phase I timeline[48]
Line Name Terminals Stations Opened
Green Line Koyambedu Alandur 7 29 June 2015
Alandur St. Thomas Mount 1 14 October 2016
Koyambedu Nehru Park 7 15 May 2017
Nehru Park Central 2 25 May 2018
Blue Line Chennai Airport Little Mount 6 21 September 2016
Little Mount AG–DMS 4 25 May 2018
AG–DMS Washermanpet 7 10 February 2019

Phase I Extension

[edit]

In 2014, a 9 km (5.6 mi) northern extension of the Blue Line was announced by the Government of Tamil Nadu. The extension would run from Washermanpet to Wimco Nagar and consist of nine stations.[49][50][51] Construction started in July 2016 with the first trial runs conducted in December 2020.[52][53] The line opened for passenger traffic on 14 February 2021, increasing the length of the operational metro system to 54.1 km (33.6 mi).[48] The expansion costed 37.7 billion (US$450 million) of which 57% was loaned by JICA.[48] In 2021, the CMRL proposed a further extension of the blue line to connect the airport with Kilambakkam at an estimated cost of 46.25 billion (US$550 million).[54][55]

Chennai Metro - Phase I Extension[48]
Line Terminals Length Stations Opened/status
Blue Line Washermanpet Wimco Nagar 9 km (5.6 mi) 8 14 February 2021
Wimco Nagar Wimco Nagar Depot 1 13 March 2022
Chennai Airport Kilambakkam 15.3 km (9.5 mi) 12 DPR prepared[56][57]

Phase II

[edit]
Chennai Metro - Phase II
Pattabiram Depot, Pattabiram ORR
Pattabiram
Hindu College
Kasturibai Nagar
Avadi railway station Avadi, Assisi Nagar
Madhavaram Depot
Murugappa College, Manjambakkam
Madhavaram Milk Colony
Vaishnavi Nagar, Velmurugan Nagar
Thirumullaivoyal,
Madhavaram
Bus Terminal
Madhavaram Mofussil Bus Terminus
Madhavaram High Road
Stedford Hospital, Sastri Nagar
Moolakadai
Ambattur OT, Retteri Junction
Ambattur, Kolathur Junction
Sembiyum
Dunlop, Srinivasa Nagar
Perambur Market
Ambattur Bypass, Villivakkam
Perambur
Ambattur Estate,
Villivakkam
Bus Terminus
Bus interchange
Ayanavaram
Villivakkam CTH Road
Otteri
Vavin 1st Main Road      
Golden Colony, Anna Nagar West
Pattalam
Park Road, Thirumangalam
Perambur Barracks Road
Padi Pudhu Nagar, Anna Nagar KV
Purusaiwalkam
Kellys
Kilpauk
Koyambedu
Koyambedu Market
Natesan Nagar
Mainline rail interchangeChetpet railway station
Virugambakkam
Chetpet
Alwarthirunagar
Saligramam Warehouse
Valasaravakkam
Saligramam, Sterling Road
Karambakkam
Vadapalani, Nungambakkam
Alapakkam
Kodambakkam Powerhouse
Kodambakkam, Anna Flyover
Porur Junction, Mugalivakkam
Mainline rail interchange Kodambakkam railway station
Porur Bypass, Ramapuram
Panagal Park, Thousand Lights
Nandanam
Thelliyaragaram, Manapakkam
Boat Club, Royapettah
Iyyapanthangal,
Chennai
Trade Centre
Bharathidasan Road, RK Salai
Kattupakkam, Butt Road
Alwarpet, Thirumayilai Thirumayilai railway station
Kumananchavadi, Alandur
Kutchery Road
Karayanchavadi, St. Thomas Mount
Mandaveli, Lighthouse
St. Thomas Mount MRTS &
St. Thomas Mount railway station
Mainline rail interchange
Greenways Road
Mullaithottam, Adambakkam Adambakkam railway station
Adyar Junction
Bus interchange Poonamallee, Vanuvampet
Adyar Bus Depot Bus interchange
Poonamallee Depot, Ullagaram
Indira-Nagar
Thiruvanmiyur Thiruvanmiyur railway station
Poonamallee Bypass, Madipakkam
MRTS line
Nazarethpet, Kilkattalai
Taramani
Chembarambakkam, Echangadu
Nehru Nagar
Kovilambakkam
Kandanchavadi
Bus interchangeKuthambakkam Bus Terminus
Perungudi
Samathuvapuram, Vellakkal
Thoraipakkam
Chettipedu, Medavakkam I
Mettukuppam
Thandalam, Medavakkam II
PTC Colony
Irungattukottai
SIPCOT
, Perumbakkam
Okkiyampet
Pennalur, Classical Tamil Institute
Karapakkam
Sriperumbudur
Okkiyam Thoraipakkam
Pattunool Chatram, ELCOT
Sholinganallur
Irungulam Industrial Estate
Sholinganallur Lake I
Mambakkam
Sholinganallur Lake II
Tirumangalam
Semmancheri Metro Depot
Sunguvarchatiram (RRTS Mainline rail interchange)
Semmancheri I
Chennai Greenfield Airport Parandur RRTS
Semmancheri II
Gandhi Nagar
Navalur
Siruseri
Siruseri SIPCOT I
Siruseri SIPCOT II


In July 2016, the Government of Tamil Nadu announced that the second phase would have three lines spanning 104 km (65 mi) with 104 stations.[58][59] Two corridors would extend from Madhavaram Milk Colony connecting with Siruseri SIPCOT and Sholinganallur respectively with the third corridor connecting Koyambedu with Lighthouse on the Marina beach. In July 2017, the state government announced an extension of Phase II, involving a section from Lighthouse up to Poonamallee Bypass with an intersection with the Madhavaram–Sholinganallur line at Alwarthirunagar. The second phase would span 118.9 km (73.9 mi) with 128 stations.[48][60] The stations for the second phase were designed to be smaller than the stations of the first phase to reduce the cost and time of construction.[61] In 2019, the Madras High Court questioned the state government on the construction method of the tunnels and its impact on the water bodies.[62] The second phase was estimated to cost 63.25 billion (US$750 million) of which 47.1 billion (US$560 million) was loaned by JICA.[48][63][64]

Construction of Madhavaram Milk Colony underground station as part of the second phase

On 20 November 2020, foundation stone for the second phase was laid and construction commenced.[65] On 14 February 2021, Prime Minister of India announced that the government has set aside 630 billion (US$7.5 billion) for the construction of the second phase and its further extension.[66] In May 2021, the CMRL awarded contracts to Tata Group, L&T and HCC-KEC for the construction of various sections of the second phase.[67] In November 2022, Alstom was awarded a contract to supply rolling stock for the second phase. The contract included a provision for the supply of 78 train sets including 36 driver-less trains.[68][69] In December 2022, a contract for the installation of tracks was given to KEC–VNC and Hitachi bagged the contract for the installation of signalling systems.[70][71] In January 2023, Rail Vikas Nigam Limited was awarded a contract for the constructions of underground stations and Linxon was given the contract for the installation of electric traction.[72][73]

In May 2023, the CMRL announced minor changes to the lines' alignment and that nine stations would be scrapped in the revised plan.[74] Hence, the total length of the second phase was reduced to 116.1 km (72.1 mi).[75] L&T was contracted for the installation of overhead equipment and control and monitoring systems.[76] Tata Projects was awarded the contract to construct select stations in October.[77] In December, the CMRL awarded the contract to ST Engineering for the installation of platform screen doors in the elevated stations of the second phase.[78] In the same month, Shellinfo was awarded a contract 420 million (US$5.0 million) for the installation of automated fare collection systems.[79] In addition to the previously ordered Alstom train-sets, the CMRL invited bids in March 2024 for the supply of 96 train-sets for the second phase.[80] As of May 2024[update], about 20 km (12 mi) of the second phase had been completed.[81]

In March 2025, the first trial run on the Phase II network was conducted on a 3 km (1.9 mi) stretch between Poonamallee and Mullaithottam on the proposed Yellow Line.[82] In April 2025, trial runs began on a 10 km (6.2 mi) stretch between Poonamallee and Porur Junction stations on the same line.[83] The RDSO conducted inspection on the same stretch in August 2025, and the Railway Board provided approval for the operation of signals on the line in December 2025.[84] In January 2025, Chennai Metro announced that the operations on Poonamallee Bypass to Vadapalani stretch will start in February 2026, with no intermediate stoppages at stations from Alapakkam to Saligramam.[85]

Chennai Metro - Phase II[74][86]
Line Terminals Length Stations Status
Purple Line Madhavaram Milk Colony Siruseri SIPCOT II 45.4 km (28.2 mi) 48 Under construction
Yellow Line Poonamallee Bypass Lighthouse 26.1 km (16.2 mi) 27
Red Line Madhavaram Milk Colony Sholinganallur 44.6 km (27.7 mi) 45
116.1 km (72.1 mi) 118[a]

Phase II Extension

[edit]

In 2022, the state government proposed an extension plan spanning 93 km (58 mi) for the three under construction lines of the second phase. The proposal involved extension of Purple Line from Siruseri SIPCOT to Kilambakkam, Yellow Line from Poonamallee to Parandur and Red Line from Koyambedu to Avadi.[87] The proposed extension of second phase lines from Siruseri to Kilambakkam, Poonamallee to Parandur, and Koyambedu to Avadi were projected to cost 54.58 billion (US$650 million), 107.12 billion (US$1.3 billion), and 67.36 billion (US$800 million) respectively.[88][89] Between late 2023 and early 2024, feasibility reports submitted by the CMRL suggested dropping the proposed extension of the purple line due to economic viability and going ahead with the planned extensions of the other two lines, spanning 59.7 km (37.1 mi).[88][89][90] In May 2024, the state government proposed a new 16 km (9.9 mi) extension from Madhavaram to Ennore.[91][92] In August 2024, a new extension from Chennai airport to Poonamallee was proposed to connect the existing airport with the planned new airport at Parandur.[93][94] In May 2024, the Government of Tamil Nadu approved both the extensions of the Red Line from Koyambedu to Pattabiram and Yellow Line from Poonamallee to Parandur at an estimated cost of 99.28 billion (US$1.2 billion) and 159.06 billion (US$1.9 billion) respectively, forwarding to Government of India for final approval.[95]

Chennai Metro - Phase II Extension
Line Terminals Length Stations Status Reference
Red Line Koyambedu Pattabiram 21.76 km (13.52 mi) 19 DPR approved by state [96][95]
Yellow Line Poonamallee Parandur 43.6 km (27.1 mi) 19 [89][97]
Lighthouse High Court 7 km (4.3 mi) TBD DPR to be prepared [98][99]
TBD Tambaram Velachery 21 km (13 mi) TBD
TBD Madhavaram Ennore 16 km (9.9 mi) TBD Feasibility to be studied [91][92]

Integration of MRTS

[edit]
Chennai MRTS is proposed to be handed over to Chennai Metro

In 2017, the state government proposed to integrate the Chennai Mass Rapid Transit System (MRTS) into the Chennai Metro.[100] In July 2018, PwC said that the merger would cost around 30 billion (US$350 million) to convert the rolling stock and install other facilities for the merger.[101] On 11 May 2022, Southern Railway of the Indian Railways granted an in-principle approval for the integration of the MRTS into the metro.[102] As per the plan, the railway would handover the MRTS to the CMRL once the expansion of the MRTS is completed. However, as of 2024, the extended second phase of the MRTS project, connecting Velachery with St. Thomas Mount was still under construction.[103][104] Once the takeover is completed, CMRL will upgrade the MRTS system including tracks, security, ticketing system and rolling stock.[105]

Metrolite

[edit]

In 2020, a light rail was proposed to connect Tambaram railway station of the existing suburban rail network with Velachery on the MRTS,[106] as part of plans to link the different urban transit lines in the city.[107][108] Feasibility studies for the project was commissioned in February 2023 by the Chennai Unified Metropolitan Transport Authority (CUMTA).[107] In March 2024, a study was commissioned to re-assess the feasibility of establishing a new corridor connecting Tambaram with Velachery with an extension to connect with existing Guindy metro station.[109] In 2025, the government decided to develop the stretch as a regular metro corridor.[98]

Others

[edit]
MetroS, the Chennai Metro headquarter building at Nandanam

The third phase of the Chennai Metro is under planning as a part of the Chennai Comprehensive Mobility Plan.[110] The CMRL is also involved in the feasibility studies for the development of metro rail transport in the cities of Coimbatore, Madurai and Tiruchirapalli.[111]

CMRL developed the Kathipara Urban Square as a multi-modal transport hub with parking and recreational areas.[112] In 2023, the CMRL proposed the development of Central Square around its headquarters with commercial complexes and multi-storied buildings.[113] In April 2025, CMRL announced that it has identified public spaces in Adyar and Velachery which can be transformed into public spaces similar to Kathipara Urban Square.[114]

Infrastructure

[edit]

Network and lines

[edit]

Chennai Metro runs on 1,435 mm (4 ft 8+12 in) standard gauge and the lines are double-tracked.[115] The trains can operate at a maximum speed of 120 km/h (75 mph), and the average operational speed is 85 km/h (53 mph).[116]

As of December 2025, the operational network consists of two colour-coded lines covering a length of 54.1 km (33.6 mi).[48][117]

Operational lines of Chennai Metro[118][48]
Line Terminal Operational Length (km) Stations
Blue Line Wimco Nagar Depot Chennai Airport 21 September 2016 32.1 26
Green Line Central St. Thomas Mount 29 June 2015 22 17
Total 54.1 41[b]

Rolling stock

[edit]
Chennai metro coaches are manufactured by Alstom

Alstom supplied the rolling stock for the first phase of the Chennai Metro.[119] For the first phase, it supplied 42 train-sets composed of four coaches.[120] The first nine train sets were imported from Brazil and the rest were manufactured at Alstom's facility at Sri City near Chennai.[120][121][122] The trains are air-conditioned with electrically operated automated sliding doors. The trains usually have a first class compartment and a dedicated section reserved for women.[123]

The trains operate on 25 kV AC electric traction.[124] The trains are connected to the grid via overhead lines and are equipped with regenerative braking with a capacity to recover 30–35% of the energy during braking.[125] The electricity is supplied by the Tamil Nadu Electricity Board, and the metro system consumed an average of 70 MW of power daily in 2014.[126] Chennai Metro also uses solar power with an installed capacity of 6.4 MWp, which contributed to about 12-15% of the energy requirement of the metro in 2023.[127]

For the second phase, Alstom was awarded a 9.47 billion (US$110 million) contract to supply 26 trainsets made of three coaches each to be deployed on the Yellow Line.[128][129] In November 2024, CMRL awarded a 36.58 billion (US$430 million) contract to BEML for the supply of 70 trainsets, made of three coaches each, to be deployed on Red and Purple lines.[130] In June 2025, CMRL placed an additional order of 32 driverless trainsets.[131]

Stations

[edit]
Full-height enclosed platform screen doors installed in the underground stations

A total of 40 stations, 22 of which are underground, are operational on the two lines of the first phase. In the underground sections, a walkway runs along the length of the corridor with cross passages every 250 m (820 ft) for the maintenance and emergency evacuation.[132] The underground stations have an average width of 200 m (660 ft) and are located at an average depth of 6.1 m (20 ft) from the ground level.[133] The average length of the stations in Phase 1 extension is about 180 m (590 ft).[134][135]

The elevated stations have three levels with the concourse level at a minimum height of 5.5 m (18 ft) above the ground level and platform level above the concourse while the underground stations have two levels and are equipped with platform screen doors.[136] The stations are air-conditioned and are equipped to be disabled and elderly friendly, with automated fare collection, public announcement system, electronic display boards, escalators and lifts.[137] Paid parking facilities are available for two wheelers in most stations and four wheelers in select stations.[138]

Depots

[edit]
Wimco Nagar depot is situated adjacent to the Wimco Nagar Depot station

Chennai Metro maintains a major depot at Koyambedu which houses maintenance workshops, stabling lines, test tracks and a washing plant for the trains. In 2022, an elevated depot at Wimco Nagar commenced operations with facilities for inspection, emergency repair, and a washing plant.[139] Three new depots at Madhavaram, Poonamallee, and Semmencherry, are planned as a part of the second phase.[140][141][142] The Madhavaram depot is planned to be the largest depot of the Chennai metro.[143] The Poonamallee depot was used for conducting trial runs in 2024.[144] In 2025, a sixth depot was planned at Pattabiram as a part of the second phase extension of the Chennai Metro.[145]

Operations

[edit]

As of 2022[update], the metro operates trains from 5:00 am to 11:00 pm. The blue line has an average frequency of every 6 minutes during peak hours and every 12 minutes during off-peak hours. On the green line, the average frequency is 12 minutes during peak hours and 18 minutes during off-peak hours.[146][147] The main operational control center (OCC) is located in Koyambedu where the movement of trains and real-time CCTV footage obtained is monitored.[148] In 2022-23, the average daily ridership was 0.25 million.[149]

Fare and ticketing

[edit]
Interior of Chennai Metro coaches

The minimum fare is 10 and the maximum fare is 50.[150][151]

There are six types of tickets issued by CMRL for travel in Chennai Metro.[152]

  • Single journey tokens, which need to be purchased each time for every journey at the ticket counter or in ticket vending machines available at all stations.
  • Stored value cards (SVC) are pre-paid, rechargeable, travel cards that can be purchased at any ticket counter against a refundable deposit, can be recharged up to at any ticket counter or in automated ticket vending machines at stations and offers discounted fares. In April 2023, National Common Mobility Card replaced the Stored value cards
  • Trip cards are for applicable for travel between the same two stations and are available in varied combinations and validity with discounted fares.
  • Tourist cards provide the cardholders unlimited rides on the Chennai Metro system for one day.
  • QR Tickets for single and return journey tickets can be bought through the CMRL mobile app with QR code ticket scanners at stations.[153]
  • National Common Mobility Card, also branded as Singara Chennai card, a stored-value cum debit card launched in 2023 in association with State Bank of India which can be used to access all major other metro and select bus transport systems in India.

Incidents

[edit]
  • On 17 June 2015, a 30-year-old man was killed and another motorcyclist injured when an iron rod fell on them at a metro construction site near Officers Training Academy at St. Thomas Mount.[154][155]
  • On 27 September 2022, a crane used for transporting iron rods crashed near Ramapuram, causing the rods to fall on a Metropolitan Transport Corporation bus and injuring the bus driver, conductor, and crane operator.[156]
  • On the night of 13 June 2025, two girders of the under-construction Poonamallee–Porur Metro section collapsed in Manapakkam, killing a 43-year-old man. CMRL imposed a fine of 10 million (US$120,000) on the contractor Larsen & Toubro for the incident.[157]

See also

[edit]

Notes

[edit]
  1. ^ Madhavaram Milk Colony station is considered as one station as it is shared between Purple and Red Lines. The existing Koyambedu station on the Green Line will be used by the Red Line.[74]
  2. ^ Two inter-change stations are shared by the lines

References

[edit]
  1. ^ "10.52 crore passengers travelled in Chennai Metro Train in 2024" (PDF). Chennai Metro (Press release). 2 January 2025. Retrieved 1 June 2025.
  2. ^ "Metro Rail: power supply, overhead equipment contract given" (PDF). Chennai Metro Rail Limited. 2 November 2015. Archived (PDF) from the original on 8 April 2023. Retrieved 31 January 2023.
  3. ^ Chennai Division, General Information (PDF) (Report). Southern Railway Zone, Indian Railways. Archived (PDF) from the original on 15 June 2024. Retrieved 1 December 2023.
  4. ^ Brief History of Chennai Division (PDF) (Report). Southern Railway Zone, Indian Railways. Archived (PDF) from the original on 15 December 2023. Retrieved 1 December 2023.
  5. ^ Institutional Development of Suburban Rail systems (PDF) (Report). Indian Railway. p. 10. Archived (PDF) from the original on 2 April 2024. Retrieved 1 December 2023. This was appreciated by the Planning Commission way back in 1965, when it took the initiative to set up Metropolitan Transport Teams (MTT) to study the transport problems of the first four metropolitan cities of Bombay, Calcutta, Delhi and Madras and to recommend policies and programs for their improvement.
  6. ^ Report No.5 of 2006 (Railways) (PDF) (Report). Comptroller and Auditor General of India. p. 2,3. Archived (PDF) from the original on 15 April 2024. Retrieved 26 December 2023.
  7. ^ Traffic and Transportation, Chapter 5 (PDF). CMDA (Report). Archived (PDF) from the original on 31 January 2012. Retrieved 19 August 2012.
  8. ^ "Development of MRTS in Chennai". Chennai Metropolitan Development Authority. Archived from the original on 12 July 2023. Retrieved 1 December 2023.
  9. ^ "MRTS services extended". Business Line. 27 January 2004. Archived from the original on 29 October 2013. Retrieved 29 July 2012.
  10. ^ "Metro is a financial success, not just a technological one". Livemint. 11 September 2007. Archived from the original on 13 November 2019. Retrieved 13 November 2019.
  11. ^ a b c d "Chennai Metro Rail Project approved by Government of India" (PDF) (Press release). Chennai Metro Rail Limited. 28 January 2009. Archived (PDF) from the original on 8 April 2023. Retrieved 1 December 2023.
  12. ^ a b c "Chennai Metro Rail FAQ". Chennai Metro Rail Limited. Archived from the original on 27 February 2018. Retrieved 16 February 2018.
  13. ^ "Center nod for Metro Rail in Chennai". The Times of India. 16 April 2008. Archived from the original on 25 June 2008. Retrieved 20 August 2010.
  14. ^ "Soma Enterprise wins Rs.199 crore Chennai Metro Rail order". Projects Today. 19 February 2009. Archived from the original on 28 April 2024. Retrieved 16 August 2010.
  15. ^ "Work commences on Chennai Metro". Projects Today. 11 June 2009. Archived from the original on 25 August 2017. Retrieved 16 August 2010.
  16. ^ Ramesh, Niranjana (10 March 2009). "Another milestone in Chennai metro to be designed by French". The Economic Times. Archived from the original on 19 October 2016. Retrieved 10 March 2009.
  17. ^ "Alstom to provide 2000 cars for Chennai's metro". The Financial Express. 11 September 2010. Archived from the original on 29 January 2023. Retrieved 18 September 2010.
  18. ^ "First Metro Rolling Stock contract in India". Alstom (Press release). 9 September 2010. Archived from the original on 15 April 2023. Retrieved 18 September 2010.
  19. ^ "L&T, Alstom JV bags Chennai Metro project". Business Standard. Archived from the original on 10 February 2018. Retrieved 14 February 2018.
  20. ^ "L&T, Alstom venture bags Chennai Metro project". The Hindu. 22 January 2011. Archived from the original on 2 November 2013. Retrieved 6 June 2016.
  21. ^ "Two firms bag 12 underground tunnels & stations work". The Times of India. 1 February 2011. Archived from the original on 3 October 2016. Retrieved 6 June 2016.
  22. ^ "Gammon India bags two Chennai Metro orders worth Rs 19.47 billion". The Economic Times. 2 February 2011. Archived from the original on 29 January 2023. Retrieved 6 June 2016.
  23. ^ "Elevated metro stations to come up at 100 places". The Times of India. 29 June 2010. Archived from the original on 5 July 2010. Retrieved 16 August 2010.
  24. ^ "Tenders awarded for 10 Metro Rail stations". The Hindu. 29 June 2010. Archived from the original on 14 August 2010. Retrieved 16 August 2010.
  25. ^ "Metro Rail awards contract for lifts". The Hindu. Archived from the original on 14 January 2016. Retrieved 6 June 2016.
  26. ^ "Siemens wins power supply contract for Chennai metro". Business Standard. 12 February 2011. Archived from the original on 18 August 2016. Retrieved 6 June 2016.
  27. ^ "Work on 'double-decker' structure at Arcot Road". The Hindu. 12 September 2011. Archived from the original on 14 January 2016. Retrieved 6 June 2016.
  28. ^ Sangameswaran, K. T. (5 April 2012). "Plea against razing part of heritage building for Metro Rail dismissed". The Hindu. Archived from the original on 7 April 2012. Retrieved 7 April 2012.
  29. ^ Raja Simhan, T. E. (24 September 2014). "Chennai Metro Rail set for trial runs between Egmore, Shenoy Nagar by middle of next year". Business Line. Archived from the original on 15 February 2016. Retrieved 2 October 2014.
  30. ^ Manikandan, K.; Srinivasan, Meera (10 January 2013). "Girder crash kills worker at Chennai Metro Rail site". The Hindu. Archived from the original on 19 April 2014. Retrieved 6 June 2016.
  31. ^ Ramakrishnan, T. (6 November 2013). "Chennai Metro Rail Test Run". The Hindu. Archived from the original on 10 November 2013. Retrieved 6 November 2013.
  32. ^ "Metro phase I: A hard, but gratifying journey". The Times of India. 10 February 2019. Archived from the original on 18 March 2020. Retrieved 1 June 2024.
  33. ^ "After several delays, first phase of Chennai metro rail service inaugurated by Jaya". First Post. 29 June 2015. Archived from the original on 14 June 2021. Retrieved 1 June 2024.
  34. ^ Sekar, Sunitha (11 January 2014). "Metro Rail worker dies as crane topples". The Hindu. Archived from the original on 27 April 2023. Retrieved 1 June 2023.
  35. ^ "Metro Rail Rolls Out a Surprise with Koyambedu-Pillar trial Run". New Indian Express. 14 February 2014. Archived from the original on 15 September 2014. Retrieved 2 October 2014.
  36. ^ "Chennai Metro holds trial on elevated section". Business Line. 14 February 2014. Archived from the original on 22 February 2014. Retrieved 2 October 2014.
  37. ^ "Chennai Metro one stop short of dream run". Deccan Chronicle. 31 August 2014. Archived from the original on 4 March 2016. Retrieved 6 June 2016.
  38. ^ "Metro rail service likely to begin in November". The Hindu. 31 August 2014. Archived from the original on 14 January 2016. Retrieved 6 June 2016.
  39. ^ Shivakumar, C (3 January 2015). "1st Phase Metro Tracks Ready for Safety Test". The New Indian Express. Archived from the original on 4 March 2016. Retrieved 6 June 2016.
  40. ^ Kannan, Ramya (7 April 2015). "Metro Rail safety inspected". The Hindu. Archived from the original on 14 January 2016. Retrieved 7 June 2016.
  41. ^ "Koyambedu-Alandur metro closer to opening". The Times of India. 7 April 2015. Archived from the original on 24 July 2016. Retrieved 7 June 2016.
  42. ^ "Conditional clearance for Metro Rail". The Hindu. 28 April 2015. Archived from the original on 14 January 2016. Retrieved 7 June 2016.
  43. ^ Chennai Metro Newsletter - August 2015 (PDF) (Report). Chennai Metro Rail Limited. 29 June 2015. Archived (PDF) from the original on 20 October 2023. Retrieved 7 June 2023.
  44. ^ "Chennai Metro newsletter, September 2016" (PDF). Chennai Metro Rail Limited. October 2016. Archived (PDF) from the original on 3 June 2024. Retrieved 1 May 2024.
  45. ^ Sekar, Sunitha (14 May 2017). "Naidu, Palaniswami flag off underground stretch of Chennai Metro". The Hindu. ISSN 0971-751X. Archived from the original on 26 February 2020. Retrieved 29 January 2019.
  46. ^ Sekar, Sunitha (25 May 2018). "Chennai Metro Rail opens two underground stretches". The Hindu. ISSN 0971-751X. Archived from the original on 27 February 2020. Retrieved 29 January 2019.
  47. ^ Simhan, TE Raja (10 February 2019). "PM Modi inaugurates Chennai Metro Rail's final leg". Business Line. Archived from the original on 26 October 2020. Retrieved 13 February 2019.
  48. ^ a b c d e f g h "Project status of Chennai Metro". Chennai Metro Rail Limited. Archived from the original on 26 September 2016. Retrieved 16 August 2010.
  49. ^ "Chennai Metro adds a station to phase-1 extension". The Hindu. 30 October 2014. Archived from the original on 14 January 2016. Retrieved 1 June 2024.
  50. ^ "Track work in Metro phase 1 extension to begin soon". The Hindu. 6 December 2018. Archived from the original on 26 February 2020. Retrieved 6 November 2019.
  51. ^ "First set of trains for Chennai metro phase 1 extension flagged-off". Business Line. 19 October 2019. Archived from the original on 5 November 2019. Retrieved 6 November 2019.
  52. ^ "Opening of phase-1 Chennai metro extension stretch to be delayed?". The New Indian Express. Archived from the original on 9 January 2021. Retrieved 9 January 2021.
  53. ^ "Chennai: Trial run between Washermanpet and Wimco Nagar Metro stations successful, says CMRL". The Indian Express. 26 December 2020. Archived from the original on 26 December 2020. Retrieved 26 December 2020.
  54. ^ "Work on 15-km Metro line from airport to Kilambakkam in Chennai suburbs may begin this year". The New Indian Express. 23 February 2021. Archived from the original on 25 April 2021. Retrieved 25 April 2021.
  55. ^ "TN to incur ₹9,000 crore this year for Chennai Metro due to delay in Centre's clearance". The Hindu. 19 February 2024. Archived from the original on 28 April 2024. Retrieved 1 April 2024.
  56. ^ "Chennai Airport-Kilambakkam Metro project set to take off". The Hindu. 20 July 2022. ISSN 0971-751X. Archived from the original on 21 July 2022. Retrieved 21 July 2022.
  57. ^ "With no funds from Centre for phase II of Metro, Airport-Kilambakkam project unlikely to be taken up now". The Hindu. 3 October 2023. Archived from the original on 10 October 2023. Retrieved 1 December 2023.
  58. ^ Sekar, Sunitha (2 August 2016). "1800 km, 180 stations: Unveiling Phase II of Metro". The Hindu. Archived from the original on 26 December 2016. Retrieved 24 January 2017.
  59. ^ Sekar, Sunitha. "Detailed project report for Phase II of Metro Rail ready". The Hindu. Archived from the original on 27 December 2016. Retrieved 24 January 2017.
  60. ^ "Metro's second phase to go up to Poonamallee". The Hindu. 20 July 2017. Archived from the original on 26 February 2020. Retrieved 1 October 2017.
  61. ^ U, Tejonmayam (28 December 2016). "Chennai: Metro rail to trim stations under phase 2". The Times of India. Archived from the original on 8 February 2017. Retrieved 24 January 2017.
  62. ^ "Was Metro tunnelling work executed without disturbing water sources, asks High Court". The Hindu. 14 March 2019. Archived from the original on 10 February 2020. Retrieved 1 May 2019.
  63. ^ "Phase-II Chennai metro project to cost Rs 36,000 cr". Business Standard. 2 March 2014. Archived from the original on 16 December 2023. Retrieved 1 December 2023.
  64. ^ "JICA extends ODA Loan of INR 4710 Cr for Chennai Metro Rail Project Phase 2 (II)". Japan International Cooperation Agency. 21 June 2022. Archived from the original on 16 December 2023. Retrieved 1 December 2023.
  65. ^ "Amit Shah to lay foundation for Chennai Metro's phase II project". The Hindu. 17 November 2020. Archived from the original on 28 April 2024. Retrieved 1 December 2023.
  66. ^ Dipak K, Dash. "Ground work for Chennai metro rail phase-2 hit". The Times of India. Archived from the original on 18 February 2021. Retrieved 19 February 2021.
  67. ^ "L&T, Tata, HCC-KEC Awarded Chennai Metro Phase 2's Contracts". Metro Rail Guy. 12 May 2021. Archived from the original on 24 February 2024. Retrieved 1 June 2024.
  68. ^ "Alstom wins €98 million contract to design and manufacture 78 metro coaches for Chennai Metro Phase-II". Alstom (Press release). 11 November 2022. Archived from the original on 16 December 2023. Retrieved 1 December 2023.
  69. ^ "Production of driverless trains for Chennai Metro Rail Phase II project begins in Sri City". The Hindu. 8 February 2024. Archived from the original on 26 February 2024. Retrieved 1 June 2024.
  70. ^ "KEC – VNC JV signs contract with Chennai Metro for track work of CMRL Phase – 2". Metro Rail News. 30 December 2022. Archived from the original on 1 January 2023. Retrieved 1 June 2024.
  71. ^ "Chennai Metro phase 2 signalling contract awarded to Hitachi for Rs 1620 crore". The News Minute. 7 December 2022. Retrieved 1 June 2024.
  72. ^ "RVNL shares rise on multiple orders from Chennai Metro". Business Today. 21 January 2023. Archived from the original on 28 June 2023. Retrieved 1 June 2024.
  73. ^ "Linxon bags traction power supply contract for Phase 2 development of Chennai metro". Metro Rail News. 3 January 2023. Retrieved 1 June 2024.
  74. ^ a b c "Chennai metro scraps nine stations in phase 2". The Times of India. 14 May 2023. Archived from the original on 2 June 2024. Retrieved 1 May 2024.
  75. ^ "Phase II– S98 (Anaimalai) TBM Breakthrough at Venugopal Nagar Shaft" (PDF) (Press release). Chennai Metro Rail Limited. 7 June 2023. Archived (PDF) from the original on 2 June 2024. Retrieved 1 May 2024.
  76. ^ "Larsen and Toubro bags two contracts worth nearly ₹770 crore for Chennai Metro Rail's phase II project". The Hindu. 24 May 2023. Archived from the original on 28 September 2023. Retrieved 1 June 2024.
  77. ^ "Chennai Metro signs contract agreement with TATA Projects for five underground stations". Business Line. 13 October 2023. Archived from the original on 22 October 2023. Retrieved 1 June 2024.
  78. ^ "CMRL phase-2: Chennai Metro Rail awards contract for install platform screen doors". The Times of India. 20 December 2023. Archived from the original on 7 January 2024. Retrieved 1 June 2024.
  79. ^ "Shellinfo Awarded Over Rs 42 Crores Contract for Chennai Metro Phase 2". Metro Rail News. 9 December 2023. Archived from the original on 2 March 2024. Retrieved 1 June 2024.
  80. ^ "CMRL Reinvites Bids for Chennai Metro Phase 2's 96 Coach Contract". Metro Rail News. 21 March 2023. Archived from the original on 5 March 2024. Retrieved 1 June 2024.
  81. ^ "20km of phase-2 metro lines across city completed in Chennai". The Times of India. 25 May 2024. Archived from the original on 26 May 2024. Retrieved 1 June 2024.
  82. ^ "Chennai Metro Rail Limited conducts its first trial run on Phase II network amid a few technical glitches". The Hindu. 30 March 2025. ISSN 0971-751X. Retrieved 29 April 2025.
  83. ^ "Amidst much cheer and excitement, Chennai Metro Rail's driverless train glides through Poonamallee-Porur stretch". The Hindu. 8 April 2025. ISSN 0971-751X. Retrieved 9 April 2025.
  84. ^ Sekar, Sunitha (17 December 2025). "Railway Board approves signalling system for Poonamallee-Porur Metro Rail stretch". The Hindu. Retrieved 19 December 2025.
  85. ^ Sekar, Sunitha (3 January 2026). "Commissioner of Metro Railway Safety inspects Phase II trains". The Hindu. Retrieved 3 January 2026.
  86. ^ Chennai Metro rail phase II (PDF) (Report). Chennai Metro Rail Limited. 10 September 2023. Retrieved 1 December 2025.
  87. ^ "Detailed feasibility report for Chennai Metro Rail's Phase 2 extension to be ready in three months". The Hindu. 26 March 2023. Archived from the original on 28 April 2024. Retrieved 1 December 2023.
  88. ^ a b "CMRL submits Detailed Feasibility Reports for Phase II project extension". The Financial Express. 22 September 2023. Archived from the original on 29 April 2024. Retrieved 30 April 2024.
  89. ^ a b c "Chennai Metro Rail submits report to extend connectivity all the way to second airport site at Parandur". The Hindu. 4 January 2024. Archived from the original on 30 April 2024. Retrieved 30 April 2024.
  90. ^ "Metro from Siruseri- Kilambakkam Bus Terminus Metro Plans Dropped, deemed non-feasible". Times Now. 9 May 2024. Archived from the original on 11 May 2024. Retrieved 11 May 2024.
  91. ^ a b Selvaraj, Vignesh (11 May 2024). "Madhavaram to Ennore metro rail extension : CMRL's decision". Oneindia (in Tamil). Archived from the original on 12 May 2024. Retrieved 17 May 2024.
  92. ^ a b "Metro Rail to prepare feasibility report for Madhavaram - Ennore corridor". Dinamani (in Tamil). 12 May 2024. Archived from the original on 18 May 2024. Retrieved 18 May 2024.
  93. ^ "Meenambakkam to Parandur airport in 1 hour by metro". The Times of India. 8 August 2024. Retrieved 9 August 2024.
  94. ^ "Chennai Metro to cut travel time from Meenambakkam to Parandur airport to just 1 hour". Times Now. 8 August 2024. Retrieved 9 August 2024.
  95. ^ a b Sundaram, Ram (2 May 2025). "TN govt gives in-principle nod for Chennai Metro link from Koyambedu to Pattabiram". The Times of India. Retrieved 2 May 2025.
  96. ^ "Six firms bid to prepare DPR for Chennai metro line to Avadi". The Times of India. 28 April 2024. Archived from the original on 2 May 2024. Retrieved 2 May 2024.
  97. ^ "T.N. government gives nod to Chennai Metro Rail's Poonamallee-Parandur corridor". The Hindu. 3 June 2025. Retrieved 19 September 2025.
  98. ^ a b "Chennai Metro Rail to begin study for building RRTS, Lighthouse - High Court and Tambaram - Velachery corridors". The Hindu. 27 March 2025. Retrieved 19 September 2025.
  99. ^ "Detailed project reports to be prepared to extend Chennai Metro from Lighthouse to High Court and Tambaram to Velachery". Business Line. 11 August 2025. Retrieved 19 September 2025.
  100. ^ "Chennai Metro-MRTS merger report in six months". The Hindu. 29 May 2017. Archived from the original on 29 February 2020. Retrieved 29 May 2017.
  101. ^ Sekar, Sunitha (19 July 2018). "Metro-MRTS merger likely to be a costly affair". The Hindu. Archived from the original on 9 November 2020. Retrieved 22 July 2018.
  102. ^ "MRTS merger with Chennai Metro gets railway's approval". The New Indian Express. 15 May 2022. Archived from the original on 15 May 2022. Retrieved 16 May 2022.
  103. ^ "Concrete girder of bridge collapses at MRTS worksite in Thillai Ganga Nagar". The Hindu. 18 January 2024. Archived from the original on 31 January 2024. Retrieved 1 March 2024.
  104. ^ "Part of bridge falls, rail project delayed again". The Times of India. 19 January 2024. Archived from the original on 31 March 2024. Retrieved 1 March 2024.
  105. ^ "Chennai: With Metro coaches and modern stations, MRTS set for big upgrade". The New Indian Express. 3 January 2018. Archived from the original on 22 October 2023. Retrieved 1 December 2023.
  106. ^ "Proposed Metrolite line likely to be rubber-tyred". The New Indian Express. 7 November 2020. Archived from the original on 25 April 2021. Retrieved 25 April 2021.
  107. ^ a b "CMRL study to explore Metrolite feasibility". The New Indian Express. 7 February 2023. Archived from the original on 1 April 2023. Retrieved 1 April 2023.
  108. ^ "Standard Specifications - Light Urban Rail Transit System: 'Metrolite'" (PDF). Ministry of Housing & Urban Affairs. Archived (PDF) from the original on 30 September 2023. Retrieved 1 December 2023.
  109. ^ "CMRL revives old network from Tambaram to Velachery and extends to Guindy". The Times of India. 6 March 2024. Archived from the original on 29 April 2024. Retrieved 30 April 2024.
  110. ^ "Feasibility report ready for ₹6,683 crore Coimbatore Metro Rail". The Hindu. 23 February 2021. ISSN 0971-751X. Archived from the original on 17 April 2021. Retrieved 25 April 2021.
  111. ^ Sekar, Sunitha (22 March 2022). "CMRL to do a feasibility study for building mass rapid transit in three cities". The Hindu. ISSN 0971-751X. Archived from the original on 21 March 2022. Retrieved 22 March 2022.
  112. ^ Selvarajan, Gautham (17 December 2021). "Chennai's Kathipara Urban Square inaugurated". The New Indian Express. Retrieved 29 April 2025.
  113. ^ "Chennai Metro Rail Limited plans to build 27-storey building at Central Square". The Hindu. 27 September 2023. Archived from the original on 30 April 2024. Retrieved 25 April 2024.
  114. ^ Sekar, Sunitha (27 April 2025). "On the lines of Kathipara Urban Square, Chennai Metro Rail plans vibrant spaces in Adyar, Velachery". The Hindu. ISSN 0971-751X. Retrieved 29 April 2025.
  115. ^ Srinivasan, Meera (3 February 2013). "Countdown to Chennai Metro begins". The Hindu. Archived from the original on 5 February 2013. Retrieved 3 February 2013.
  116. ^ "Metro rail train zips over city roads". The Hindu. 6 June 2016. Archived from the original on 26 October 2023. Retrieved 1 December 2023.
  117. ^ "CMRL Phase 1 extension Washermanpet and Wimco nagar". Chennai Metro Rail Limited. 5 November 2016. Archived from the original on 25 July 2021. Retrieved 7 July 2021.
  118. ^ "Chennai Metro, line map" (PDF). Chennai Metro Rail Limited. Archived (PDF) from the original on 8 December 2023. Retrieved 1 December 2023.
  119. ^ "Alstom completes in Lapa plant the first train for Chennai metro, in India" (Press release). Alstom. May 2013. Archived from the original on 21 April 2016. Retrieved 6 June 2016.
  120. ^ a b Sekar, Sunitha (29 June 2018). "Phase II to have six and ten-coach Metro trains". The Hindu. Archived from the original on 29 January 2020. Retrieved 15 July 2018.
  121. ^ "First coach for Chennai Metro by April 2013: Alstom Transport". Business Line. Archived from the original on 2 November 2013. Retrieved 6 June 2016.
  122. ^ Sekar, Sunitha (28 October 2013). "Chennai Metro to have 1st class compartment". The Hindu. Archived from the original on 21 March 2014. Retrieved 2 March 2014.
  123. ^ Sekar, Sunitha (18 July 2014). "All aboard, Chennai Metro". The Hindu. Archived from the original on 15 February 2016. Retrieved 15 July 2018.
  124. ^ "Alstom to provide 168 cars for Chennai's metro for 243 million" (Press release). Alstom. 1 September 2010. Archived from the original on 15 April 2023. Retrieved 6 June 2023.
  125. ^ "First ride in a Chennai Metro train". The Hindu. Archived from the original on 14 January 2016. Retrieved 6 June 2016.
  126. ^ "Metro rail sets up units to power trains, stations to meet year-end deadline to start services". The Times of India. 15 April 2014. Archived from the original on 18 April 2014. Retrieved 18 April 2014.
  127. ^ Sekar, Sunitha (1 October 2023). "Chennai Metro Rail to install more solar power plants in rooftop and parking spaces". The Hindu. Archived from the original on 17 January 2024. Retrieved 17 January 2024.
  128. ^ "Alstom wins €98 million contract to design and manufacture 78 metro coaches for Chennai Metro Phase-II". Alstom (Press release). 11 November 2022. Retrieved 8 June 2025.
  129. ^ "Alstom Awarded Chennai Metro Phase 2's 78 Coach Contract". The Metro Rail Guy. 27 July 2022. Retrieved 8 June 2025.
  130. ^ Fatakia, Hormaz (28 November 2024). "PSU Order Win: BEML bags ₹3,658 crore contract from the Chennai Metro". CNBC TV18. Retrieved 8 June 2025.
  131. ^ "Alstom to supply 96 additional Metropolis driverless metro cars for Chennai Metro Phase II". Alstom (Press release). 5 June 2025. Retrieved 8 June 2025.
  132. ^ Sekar, Sunitha (10 August 2014). "First underground Metro network by December 2015". The Hindu. Archived from the original on 15 February 2016. Retrieved 4 October 2014.
  133. ^ "Metro's underground frame" (PDF). Chennai Metro Rail Limited. 20 September 2013. Archived (PDF) from the original on 26 December 2023. Retrieved 1 December 2023.
  134. ^ "Metro Phase 1 extension tunneling nears completion". The Hindu. 25 September 2017. Archived from the original on 26 February 2020. Retrieved 29 September 2017.
  135. ^ "CMRL's compact stations have their own fan club". The Hindu. 29 June 2018. Archived from the original on 30 January 2020. Retrieved 15 July 2018.
  136. ^ Chennai Metro Investment Project (PDF) (Report). Asian Development Bank. Archived (PDF) from the original on 4 June 2023. Retrieved 30 August 2023.
  137. ^ Sekar, Sunitha (20 January 2014). "No clarity on access at Chennai Metro stations yet, say disabled". The Hindu. Archived from the original on 4 February 2014. Retrieved 6 June 2016.
  138. ^ Parking Facilities Availability 2018 (PDF) (Report). Chennai Metro Rail Limited. Archived (PDF) from the original on 8 June 2019. Retrieved 16 August 2010.
  139. ^ Sekar, Sunitha (16 July 2014). "Chennai Metro to get a second depot". The Hindu. Archived from the original on 15 February 2016. Retrieved 4 October 2014.
  140. ^ "Contract Agreement Signed for construction of Operation Control Centre at Madhavaram Depot of CMRL Phase II" (PDF) (Press release). Chennai Metro Rail Limited. 20 July 2023. Retrieved 1 May 2024.}: CS1 maint: url-status (link)
  141. ^ "Chennai Metro Rail to build 3rd depot for Phase II in Semmanchery". DT Next. 13 July 2024. Retrieved 4 May 2025.
  142. ^ "Phase II Map" (PDF). Chennai Metro Rail Limited. Retrieved 1 June 2025.
  143. ^ "Madhavaram to get Chennai's largest metro depot". The Times of India. 4 March 2021. Retrieved 4 October 2025.
  144. ^ "Metro Rail's first driverless train likely to go through trial run on October 26 at Poonamallee Depot". The Hindu. 21 October 2024. Retrieved 19 September 2025.
  145. ^ Sekar, Sunitha (22 January 2025). "Chennai Metro Rail to link areas from Koyambedu to Pattabiram". The Hindu. Retrieved 20 April 2025.
  146. ^ "Single train trip to equal 160 buses, 3000 cars and 6000 bikes". The Hindu. 29 August 2012. Archived from the original on 30 August 2012. Retrieved 1 December 2023.
  147. ^ Timings of Chennai Metro Rail As of January 2022 (PDF). Chennai Metro Rail (Report). Archived (PDF) from the original on 25 January 2022.
  148. ^ Karthikeyan, K. (26 July 2014). "High tech control room for Chennai metro". Deccan Chronicle. Archived from the original on 4 October 2014. Retrieved 4 October 2014.
  149. ^ "25.01 crore passengers have travelled in Chennai Metro Train from 29th June 2015 to 31st December 2023 9.11 crore passengers travelled in Chennai Metro Train in 2023" (PDF). chennaimetrorail.org. Archived from the original (PDF) on 5 January 2024.
  150. ^ Sekar, Sunitha (11 February 2019). "Chennai Metro: Now, ride from Washermanpet to airport takes just 40 minutes". The Hindu. Archived from the original on 27 March 2019. Retrieved 11 February 2019.
  151. ^ Chennai Metro fare table (PDF) (Report). Chennai Metro Rail Limited. Archived (PDF) from the original on 16 December 2023. Retrieved 6 November 2023.
  152. ^ "Tickets issued by CMRL". Chennai Metro Rail Limited. Archived from the original on 6 September 2019. Retrieved 6 November 2019.
  153. ^ "Chennai Metro to issue printed QR code tickets". The Times of India. 24 October 2021. Archived from the original on 27 April 2022. Retrieved 27 April 2022.
  154. ^ "Software techie dies as iron rod falls on him". The New Indian Express. 17 June 2015. Archived from the original on 29 June 2016. Retrieved 6 June 2016.
  155. ^ "Chennai Techie Killed As Rod From Under-Construction Metro Station Falls on Him". NDTV. Archived from the original on 25 October 2023. Retrieved 16 September 2025.
  156. ^ "Second accident at Chennai metro site in less than a month, 3 injured in crane crash". The News Minute. 27 September 2022. Retrieved 27 September 2025.
  157. ^ "L&T Fined Rs 1 Crore After Deadly Girder Collapse At Chennai Metro Site". NDTV. Archived from the original on 22 June 2025. Retrieved 19 August 2025.
[edit]

This article is sourced from Wikipedia. Content is available under the Creative Commons Attribution-ShareAlike License.